Yesterday was devoted to perform tests on RD2.L8 and RQ4.L8
RD2.L8 has been successfully commissioned up to PNO.8d (Current cycle up to nominal current)
Missing tests for RD2.L8: Fast Power Abort from PIC (PNO.9). The detection threshold needs to be modified. Possibly done while powering at unison (like PNO.9 for RQ5)
RQ4.L8:
Unbalanced cycle up to nominal (3610 A) for B1 and 2000 A for B2. While ramping B1 converter tripped. The attempt of PO expert to recover control made the quench detector trip (same problem as last week)
Second trial of unbalanced cycle up to nominal: with B1 at nominal current and B2 ramping up to nominal, the latter quenched at 3590 A. Test failed.
Proposal for the activity of today (30/05/2007)
Complete P2N of all the 120-80A correctors of Q4 and Q5.
Continue P2N of RQ4.L8. Two options: * Unbalanced ramp up and quench with both apertures at nominal current (PNO.7a) or/and * Unbalanced cycle and quench with one aperture at nominal and the other at 50%.
ElQA activities: Morning: * Full qualification of the 3 circuits selected on DFBAN * TFM on circuits powered via DFBMH * preparation for the HV qualification of the 600A circuits Afternoon * HV qualification on 600 A circuits powered via DFBAO