RD2.L8 has been successfully commissioned up to PNO.10 (last step before Squeezing tests)
Proposal for the activity of next week.
Complete P2N of all the 120-80A correctors of Q4 and Q5.
Continue P2N of RQ4.L8
Continue powering RQ4.L8
Continue powering the correctors (4 circuits have already passed the first 2 steps, three more are available).
Possible powering of the whole matching section.
Powering of the arc 60 A orbit correctors, according to humidity conditions.
Continue installation of plastic bags on DFBAN and DFBMH.
Check the status of condensation of the 13kA leads of DFBAO which have copper laminations and no plastic bags; check the status of the 6kA lead of DFBMA which has copper laminations and no plastic bags.
Installation of ventilators on the 60 A orbit correctors leads.
ElQA on the selected circuits: see presentation of Davide in the last post.
Quench heaters qualification, without interference with ElQA.