Powering Tests - Sector 7-8 - 30/05/2007

The day was fully devoted to perform tests on D2.

    • RD2.L8 has been successfully commissioned up to PNO.10 (last step before Squeezing tests)

Proposal for the activity of next week.

  • Complete P2N of all the 120-80A correctors of Q4 and Q5.
  • Continue P2N of RQ4.L8

  • Continue powering RQ4.L8
  • Continue powering the correctors (4 circuits have already passed the first 2 steps, three more are available).
  • Possible powering of the whole matching section.
  • Powering of the arc 60 A orbit correctors, according to humidity conditions.

  • Continue installation of plastic bags on DFBAN and DFBMH.
  • Check the status of condensation of the 13kA leads of DFBAO which have copper laminations and no plastic bags; check the status of the 6kA lead of DFBMA which has copper laminations and no plastic bags.
  • Installation of ventilators on the 60 A orbit correctors leads.

  • ElQA on the selected circuits: see presentation of Davide in the last post.

  • Quench heaters qualification, without interference with ElQA.

Comments:

Edit | Attach | Watch | Print version | History: r2 < r1 | Backlinks | Raw View | Raw edit | More topic actions...
Topic revision: r1 - 2007-05-29 - MirkoPojer
 
    • Cern Search Icon Cern Search
    • TWiki Search Icon TWiki Search
    • Google Search Icon Google Search

    HCC All webs login