Test Report from Tuesday 19.07.2007
- RQD.A78:
- Transfer function measurements with 60A converter completed OK
- PCC Circuit Config tests completed
- PIC2 - All steps completed OK except:
- Circuit discharge from power converter: switches were not rearmed after PM data generation - Test to be repeated
- Discharge request from PIC - to be done
- RQF.A78:
- Transfer function measurements with 60A converter completed OK
- PCC Circuit Config tests completed
- PIC2 - All steps completed OK up to Powering Failure test (included)
- RQ4.L8 and RD2.L8:
- Tests 1 and 2 proposed by MPP completed but without provoking an artificial quench at the end of the second. Detection threshold still at 20mV. Still no quench. Further research to be done.
- RCO.A78B1 powered below 20A for QPS analysis. The circuit is still blocked till the new sofware is uploaded.
Test Plan for Wednesday 20.07.2007
- Resolution of cable signal/interlock swap F/D
- RQD.A78 (from the CCC):
- Last two steps of PIC2
- PLI1 (750A)
- PLI2 (2000A)
- PLI3 (6500A)
- RQF.A78 (from the CCC):
- Complete PIC2
- First steps of PLI1,2,3 if possible
- RB.A78
- IST Energy extraction tests, PIC1, connection of the leads
- Matching section:
- Type analysis of the power converters
- Analyse boil-off data and eventually repeat a more complete boil-off
- Waiting for new proposals from MPP
- 120A converter on Q5 type tests