Transfer function measurements with 60A converter completed OK
PCC Circuit Config tests completed
PIC2 - All steps completed OK except:
Circuit discharge from power converter: switches were not rearmed after PM data generation - Test to be repeated
Discharge request from PIC - to be done
RQF.A78:
Transfer function measurements with 60A converter completed OK
PCC Circuit Config tests completed
PIC2 - All steps completed OK up to PC Permit test (included)
RQ4.L8 and RD2.L8:
Tests 1 and 2 proposed by MPP completed but without provoking an artificial quench at the end of the second. Detection threshold still at 20mV. Still no quench. Further research to be done.
RCO.A78B1 powered below 20A for QPS analysis. The circuit is still blocked till the new sofware is uploaded.