Powering Tests Sector 7-8 - 21.06.2007

Test Report of Wednesday 20.6.2007

  • RQF.A78
    • PIC2 completed up to Fast Power Abort from PIC - Test OK

  • RQD.A78
    • PIC2 tests completed - OK
    • PLI1 tests at 760A completed - OK
    • PLI2 tests at 2000A completed - OK
    • PLI3 started. RQD.A78 circuit ramped up successfully to 6400A, kept there for more than one hour. - OK
    • Champagne and pictures
    • PLI3.1 test completed - Magnet ramped up to 6500A and down to 350A successfully!!

  • Matching section
    • Type tests on different circuits performed by AB/PO

Planning for Thursday 21.06.2007

  • RQD.A78
    • PLI3.2 Discharge request
    • PLI3.3 Quench heater discharge

  • RB.A78
    • After tests completed in RQD.A78 (in parallel):
      • QPS IST tests
      • Connection of the current leads in DFBAO and DFBAN
    • PIC1
    • Connection of the 60A converter - Transfer function measurement
    • Cabling repair 600A - RCS, RCD circuits.
    • Wait for DFBAN release from ACR

  • 600 Circuits - Further measurements by QPS - Depending on Reiner's progress in RB, which has full pripority.

  • Matching section
    • Type tests AB/PO continue
    • ACR checks on the DFBMA current leads with D2 at nominal current

Edit | Attach | Watch | Print version | History: r3 < r2 < r1 | Backlinks | Raw View | WYSIWYG | More topic actions
Topic revision: r3 - 2007-06-21 - AntonioVergara
 
    • Cern Search Icon Cern Search
    • TWiki Search Icon TWiki Search
    • Google Search Icon Google Search

    HCC All webs login