Test Report of Wednesday 21.06.2007
- RQF.A78
- PIC2 completed up to Fast Power Abort from PIC - Test OK
- RQD.A78
- PIC2 tests completed - OK
- PLI1 tests at 760A completed - OK
- PLI2 tests at 2000A completed - OK
- PLI3 started. RQD.A78 circuit ramped up successfully to 6400A, kept there for more than one hour. - OK
- Champagne and pictures
- PLI3.1 test completed - Magnet ramped up to 6500A and down to 350A successfully!!
- Matching section
- Type tests on different circuits performed by AB/PO
Planning for Thursday 22.06.2007
- RQD.A78
- PLI3.2 Discharge request
- PLI3.3 Quench heater discharge
- RB.A78
- After tests completed in RQD.A78, QPS IST tests
- PIC1
- Connection of the current leads in DFBAO and DFBAN