Powering Tests Sector 7-8 - 21.06.2007

Test Report of Wednesday 21.06.2007

  • RQF.A78
    • PIC2 completed up to Fast Power Abort from PIC - Test OK

  • RQD.A78
    • PIC2 tests completed - OK
    • PLI1 tests at 760A completed - OK
    • PLI2 tests at 2000A completed - OK
    • PLI3 started. RQD.A78 circuit ramped up successfully to 6400A, kept there for more than one hour. - OK
    • Champagne and pictures
    • PLI3.1 test completed - Magnet ramped up to 6500A and down to 350A successfully!!

  • Matching section
    • Type tests on different circuits performed by AB/PO

Planning for Thursday 22.06.2007

  • RQD.A78
    • PLI3.2 Discharge request
    • PLI3.3 Quench heater discharge

  • RB.A78
    • After tests completed in RQD.A78, QPS IST tests
    • PIC1
    • Connection of the current leads in DFBAO and DFBAN