Provisional correction of the detection threshold of the bus-bar quench detector.
TF measurement - Test OK after some corrections done in one QPS crate
RB converter connected to the circuit
Circuit ramped up to 350A with the bus-bar quench detection threshold increased. Loop properly closed!
Some modifications needed in the QPS bus-bar quench detector - Circuit ramped up again to 350A with QPS in operational conditions!!
PCC Circuit Config - TEST OK!
RQF.A78 (6500A)
PLI3.2 - Energy extraction discharge - Test OK
PLI3.3 - Quench heater discharge on 12L8 SSS - Test OK
600A Correctors
PCS tests on the circuits: RQT12.L8B1, RQS.L8B1, RCO.A78B1 - Going on
DFBMA refilled and cooled down in a couple of hours
60A Closed Orbit Correctors: PCC in 16 converters
Test Plan for Tuesday 26.06.2007
RB.A78
PIC2
PLI1 (760A)
PLI1.1 - Current cycle
PLI1.2 - Energy extraction discharge (quench to a current lead)
PLI1.3 - Powering Failure from PC
PLI1.4 - FPA from PIC
PLI1.5 - Quench heater discharge on LBBRG.10L8 (magnet 1030)
PLI2 (2000A)
PLI2.1 - Current cycle
PLI2.2 - Energy extraction discharge (quench to a current lead)
PLI2.2b - SPA from PIC
PLI2.3 - Quench heater discharge on LBBRA.13L8 (magnet 3002) and LBARA.13R7 (magnet 1054)
Matching Section: Powered to the same conditions of the triple quench on 31/06 once the quench detection threshold has been increased to operational values.
60A closed orbit correctors: PCC and P2N
RQF.A78 or RQD.A78
Type tests
Quench campaign:
RQF and RQD ramped up together to 6500A. Quench TWO quadrupoles in different cryogenic cells simmultaneously.
RQF and RQD ramped up together to 6500A. Quench FOUR quadrupoles in different cryogenic cells simmultaneously.
600A correctors
Study and debugging of the quench detectors going on.