600A Circuit Program | ||
---|---|---|
1 | PCS tests for RQTF.A78B1, RQTF.A78B2 | Reiner, Bob, Sandor |
1 | PCC & PIC2 for RSD1.A78B1, RSD2.A78B2, RSF2.A78B1, RSF2.A78B2, RCS.A78B1, RCS.A78B2 | Markus, Valerie |
2 | PCS tests for RSD1.A78B1, RSD1.A78B2, | Reiner, Bob, Sandor |
2 | PCC & PIC2 for RQTD.A78B1, RQTD.A78B1 | Markus, Valerie |
3 | PCS tests for the rest (RSD2.A78B1, RSD2.A78B2, RSF2.A78B1, RSF2.A78B2, RCS.A78B1, RCS.A78B2, RQTD.A78B1, RQTD.A78B2, RSF1.A78B1, RSF1.A78B2) | Reiner, Bob, Sandor |
4 | PCC, PIC2 and PCS tests of RQS.A78.B2, RQS.R7B1, RQTL10.R7B1 | Markus, Valerie, Reiner, Bob, Sandor |
5 | PCS tests of RQ6.R7B1, RQ6.R7B2 | Reiner, Bob, Sandor |
6 | Performance and type tests of RQS.L8B1, RQT12.L8B1, RQTF.A78B1, RCS.A78B1 | Valerie, David |
Main magnets | ||
---|---|---|
1 | Quadruple quadrupole quench | AB/PO, AT/MEL, HCC |
60A orbit correctors | ||
---|---|---|
1 | P2N | AB/PO, HCC |
Power Converter Studies | ||
---|---|---|
1 | RQF.A78 and RB.A78 stability and reproducibility | Valerie, David |
2 | RCBCH5.L8B1 and RCBYH4.L8B2 stability and reproducibility | Valerie, David |
Sector studies | ||
---|---|---|
1 | Power converter tracking tests (RB, RQF, RQD) | Valerie, David |
2 | LSA tracking tests (RB, RQF, RQD, Q4, Q5, D2 and some 600 A corrector circuits) | Mike, David |
3 | Matching Section: Powering of RD2.L8 and RQ4.L8 with DFBMA at minimum liquid operational level (31%) - RD2.L8 quench detector threshold at 20mV | Amalia, Glyn, Andzrej |
4 | Long duration tests of all available circuits – Minimum 8-hour run (overnight tests?) | HCC |
ElQA | ||
---|---|---|
1 | RQS.A78.B2, RQS.R7B1, RQTL10.R7B1 | Davide |
2 | All the circuits in the sector via DFBs 2 days | Davide |
3 | 3006 additional diagnostic 1.5 days | Davide |
4 | Q5 correctors (4) in DFBMC 1 day | Davide |
5 | Installation of monitoring system for warm-up | Davide |
6 | Boiloff test on DFBMA on the two chimneys 120A circuits | Davide |
7 | Remaining two third of 60A orbit correctors at cold | Davide |