Powering Tests Sector 7-8 _ 29/06/2007

D2-Q4 study in the afternoon

The following cycle has been executed on D2-Q4, to study stability at minimum liquid helium level in DFBMA:

  • with nominal liquil helium level inside the DFBMA, RD2.L8 and RQ4.L8B1/B2 to I_min_op
  • lower liquid helium level to 31%
  • ramp of RD2.L8 to 6kA with 18 A/s ramp rate; once at nominal, ramp of RQ4.L8B1/B2 to 3610 A with 10A/s ramp rate
  • plateau of 30 min, then ramp RQ4.L8B1/B2 to I_min_op (RD2.L8 always at nominal)
  • wait 2 min and ramp RQ4.L8B2 to 3610A at 10 A/s and RQ4.L8B1 to 1900A at 10A/s
  • plateau of 20 min
  • power permit removed on all PCs and SPA initiated withou quench.

Test result: successful!

Edit | Attach | Watch | Print version | History: r1 | Backlinks | Raw View | WYSIWYG | More topic actions
Topic revision: r1 - 2007-06-29 - MirkoPojer
 
    • Cern Search Icon Cern Search
    • TWiki Search Icon TWiki Search
    • Google Search Icon Google Search

    HCC All webs login