PlanningW27_020707.xls:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint8x2007x07x02x21x18/PlanningW27_020707.xls
Test Report from Monday 02.07.2007
* RQF.A78, RQF.A78 and RB.A78: Stability tests completed.
* RCBCH5.L8B1 stability test completed.
* 60A Closed Orbit Correctors: PNO completed for all the circuits released by ElQA. Tests OK except for two natural quenches in the circuits: RCBH28.L8B2 and RCBH25.L8B1
* 600A Correctors:
- PCC and PIC2 completed for all the circuits available in DFBAO except RQTD.A78B1 and RQTD.A78B2
- PCS completed successfully for RQTF.A78B1 and RQTF.A78B2
- RCS.A78B2 - PCS.2 (50A) PCS.3 (100A) - Test OK
- RCS.A78B1 - PCS.2 failed due to inversed polarity
Test Plan for Tuesday 03.07.2007
See file attached