Right 8: leak localised in C'. Repair going on. Final test wil be done once the SSS repairs are finished.
Electrical non-conformities on instrumentation cables of the power converters will be closed by the end of the week.
LHCb compensator tests will last till tomorrow Friday
Installation of the instrumentation rods in DFBs Right 8 - COMPLETED
Water pump check Point 8 planned for this week
Planned activities
PIC-PC interface test - Wk 43
Room temperature vacuum and collimator works (wks 43-46), bake-out (wks 47 -48)
ATLAS-RP cable installation - Wks 48-49
DFBXH:
Ineo cabling - Wk 43
Installation of the removed water-cooled cable - Flohe Wk ?
New cleaning of the DFBXH, the instrumentation will have to be removed and the DFBX re-validated by AT-MEL afterwards - Wk ?
MB1158 diode: electrical continuity tests - Monday 15 Oct
Flexible water cable reconnection DFBs Left 1 - Week 42
General
AUG test on October 19 - Real impact will be described today
Cooling water shut-down - Wks 42-44 - All the cryogeninc activities will be stopped. The purging acitivities required to continue with he vacuum tests could be carried out using a temporary solution. Paul will ask Francois to go ahead with it.
A latest date for taking a decission about repairing or not the DFBAs has to be set for not jeopardizing the starting date of the flushing