SCT in UJ33

PowerPoint GlobalAnalysis24hHR_UJ33.ppt:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint3x2007x05x04x18x27/GlobalAnalysis24hHR_UJ33.ppt

  • During the 24hr heat run major problems were found (for a more detailed description see the attached file):
1 - Over-heating of the systems in UJ33 (central part) – TS-EL will re-routing the cables inside the UJ33.

2 - Over- heating of the cables in the tunnel side RZ33 – a vertical cable tray will be positioned parallel to the TS-CV cooling water supports. The tray will host one of the three cable layers that are now placed on the same tray.

  • The re-routing cable works will last approximately up to the third week of June. The integration/cost studies are on going and the possible co-activities interfering with the preparation for the cooldown of the A34 are being taken into account.
A meeting to up-date the "status of the art" is foreseen for Monday 14th. Details will be given.

  • During the inspection of the UJ33 P. Proudlock commented:

1 - ODH system must be foreseen in UJ33 - the DFBLC inside the UJ makes it indispensable

2 - Rectangular ducts (for the geometers) must be closed during the heat-run

Edit, attach file or add comment


Created by Main.BorisBellesia on 2007-04-18 - 13:19

SCT in UJ33 - 18th April

PDF RAT_20071704.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint3x2007x04x18x13x15/RAT_20071704.pdf

********************************** **********************************

In the Minutes:

* Resume of the two 8hr heat runs

* List of the contact people of the concerned system during the 24hr heat run

********************************** **********************************

Schedule:

22.03 DONE Polarity Check
30.03 DONE CCC tests: preparation for the 8hr run
16.04 DONE First 8hr HEAT RUN ; re-scheduled
17.04 DONE Second 8hr HEAT RUN
18.04 - CCC tests: preparation for the 24hr run
19.04 - 24hr HEAT RUN
20.04 - AUG - UPS test
21.05 - EE 4hr run

Edit, attach file or add comment


Created by Main.BorisBellesia on 2007-04-13 - 15:28

SCT in UJ33 - 12th April

PDF RAT_20071204.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint3x2007x04x13x15x22/RAT_20071204.pdf

PDF SOC_settings_8hrun_UJ33.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint3x2007x04x13x15x22/SOC_settings_8hrun_UJ33.pdf

********************************** **********************************

1 - TS-CV confirmed that the ED circuit of the sector 2-3 will be normally operated the 16th-17th and the 19th.

********************************** **********************************

2 - In attachment: the current of each PC in UJ33 in the 4 steps of the 8hr run.

* HEAT RUNS Schedule:

22.03 DONE Polarity Check
30.03 DONE CCC tests: preparation for the 8hr run
16.04 - First 8hr HEAT RUN ; re-scheduled
17.04 - Second 8hr HEAT RUN
18.04 - CCC tests: preparation for the 24hr run
19.04 - 24hr HEAT RUN
20.04 - AUG - UPS test
21.05 - EE 4hr run

Edit, attach file or add comment


Created by Main.BorisBellesia on 2007-04-04 - 12:31

SCT in UJ33 - 4th April

PDF RAT_20070404.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint3x2007x04x04x12x30/RAT_20070404.pdf

Comments:

Edit, attach file or add comment


Created by Main.BorisBellesia on 2007-04-02 - 19:02

SCT in UJ33 - 2nd April

PDF RAT_20070402.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint3x2007x04x02x18x56/RAT_20070402.pdf

Comments: HEAT RUN CANCELLED

  • Maintenance of the water-cooling circuits coming form Point 2 providing water also to the cooling circuits of the power converters in UJ33 was planned to be performed between 02.04 (today) and the 20.04. This manipulation was not taken into account during the planning of the SCT in UJ33.

  • The maintenance caused the stop of the tests and was irreversible: it will be not possible recuperate the cooling power until the end of the intervention.

  • The tests has been rescheduled in agreement with TS-CV. The priority will be given to the work in SX2 (the primary circuit) in order that the water in UJ33 will be available the 16.04.

HEAT RUNS Schedule:

22.03 DONE Polarity Check
30.03 DONE CCC tests: preparation for the 8hr run
2.04 CANCELLED First 8hr HEAT RUN
16.04 - First 8hr HEAT RUN ; re-scheduled
17.04 - Second 8hr HEAT RUN
18.04 - CCC tests: preparation for the 24hr run
19.04 - 24hr HEAT RUN
20.04 - AUG - UPS test
23.04 - EE 4hr run

Edit, attach file or add comment


Created by Main.JacekSzkutnik on 2007-03-30 - 12:55

SCT in UJ33 - 30th March

PDF RAT_20070330.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint3x2007x03x30x12x53/RAT_20070330.pdf

************ 8hr HAET RUN: Monday 02.04 - Tuesday 03.04 ************

HEAT RUNS Schedule:

22.03 ON GOING Polarity Check
30.03 ON GOING CCC tests: preparation for the 8hr run
2.04 - First 8hr HEAT RUN
3.04 - Second 8hr HEAT RUN
11.04 - CCC tests: preparation for the 24hr run
12.04 - 24hr HEAT RUN
12.04 - AUG - UPS test
13.04 - EE 4hr run

Edit, attach file or add comment


Created by Main.BorisBellesia on 2007-03-26 - 19:51

SCT in UJ33 - 26th March

PDF RAT_20070326.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint3x2007x03x26x19x45/RAT_20070326.pdf

HEAT RUNS

22.03 - Polarity Check
30.03 - CCC tests: preparation for the 8hr run
2.04 - First 8hr HEAT RUN
3.04 - Second 8hr HEAT RUN
11.04 - CCC tests: preparation for the 24hr run
10.04 - 24hr HEAT RUN
12.04 - AUG - UPS test
13.04 - EE 4hr run

Edit, attach file or add comment


Created by Main.BorisBellesia on 2007-03-23 - 17:22

SCT in UJ33 - 23th March

PDF RAT_20070323.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint3x2007x03x23x17x16/RAT_20070323.pdf

PDF Etude-sect-cablesDC-UJ33-tot.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint3x2007x03x23x17x16/Etude-sect-cablesDC-UJ33-tot.pdf

ATTACHED: Machine Profile for the 8hr run in UJ33: Power Converters Utilization Factors

EE sys IST

6.03 DONE 600A EE systems IST - DFBLC
12.03 DONE 600A EE systems IST - DFBAE
16.03 DONE 600A EE systems IST - DFBM
6.03 DONE 13kA EE systems IST - L7
13.03 DONE 13kA EE systems IST - R7
DFBLC
14.03 DONE 600A no EE PC – IST
15.03 DONE 600A-EE interlock tests
15.03 DONE 600A-EE PC - IST
DFBAE+120A UJ33L
20.03 DONE 600A no EE PC; IST
23.03 DONE 600A-EE Interlock tests
23.03 DONE 600A-EE powering
28.03 DONE 120A; powering
DFBMD - L&R
29.03 DONE 120A - DFBM - powering
29.03 DONE 600A-EE interlock tests
29.03 DONE 600A-EE powering
WARM-MAGN. PC+120A UJ33R
2.04 DONE 600A - Warm magnets
4.04 DONE 120A 1; powering
HEAT RUNS
5.04 - 8hr HEAT RUN
6.04 - CCC tests
10.04 - 24hr heat run test
2.04 - Polarity Check
12.04 - EE 4hr run
13.04 - AUG- UPS test

Edit, attach file or add comment


Created by Main.MatteoSolfaroli on 2007-03-21 - 14:25

SCT in UJ33 - 21st March

PDF RAT_20070321.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint3x2007x03x21x14x20/RAT_20070321.pdf

Comments: EE sys IST

6.03 DONE 600A EE systems IST - DFBLC
12.03 DONE 600A EE systems IST - DFBAE
16.03 DONE 600A EE systems IST - DFBM
6.03 DONE 13kA EE systems IST - L7
13.03 DONE 13kA EE systems IST - R7
DFBLC
14.03 DONE 600A no EE PC – IST
15.03 DONE 600A-EE interlock tests
15.03 DONE 600A-EE PC - IST
DFBAE+120A UJ33L
20.03 ON GOING 600A no EE PC – IST
23.03 DONE 600A-EE Interlock tests
23.03 DONE 600A-EE powering
28.03 DONE 120A – powering
DFBMD - L&R
29.03 - 120A - DFBM - powering
29.03 - 600A-EE interlock tests
29.03 - 600A-EE powering
WARM-MAGN. PC+120A UJ33R
2.04 ONGOING 600A - Warm magnets
4.04 - 120A – powering
HEAT RUNS
5.04 - 8hr HEAT RUN
6.04 - CCC tests
10.04 - 24hr heat run test
2.04 - Polarity Check
12.04 - EE 4hr run
13.04 - AUG- UPS test

Edit, attach file or add comment


Created by Main.BorisBellesia on 2007-03-19 - 11:36

SCT in UJ33 - 19th March

PDF RAT_20070319.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint3x2007x03x19x11x30/RAT_20070319.pdf

EE sys IST

6.03 DONE 600A EE systems IST - DFBLC
12.03 DONE 600A EE systems IST - DFBAE
16.03 DONE 600A EE systems IST - DFBM
6.03 DONE 13kA EE systems IST - L7
13.03 DONE 13kA EE systems IST - R7
DFBLC
14.03 DONE 600A no EE PC – IST
15.03 DONE 600A-EE interlock tests
15.03 DONE 600A-EE PC - IST
DFBAE+120A UJ33L
20.03 ON GOING 600A no EE PC – IST
23.03 DONE 600A-EE Interlock tests
23.03 ON GOING 600A-EE powering
28.03 - 120A – powering
DFBMD - L&R
29.03 - 120A - DFBM - powering
29.03 - 600A-EE interlock tests
29.03 - 600A-EE powering
WARM-MAGN. PC+120A UJ33R
2.04 - 600A - Warm magnets
4.04 - 120A – powering
HEAT RUNS
5.04 - 8hr HEAT RUN
6.04 - CCC tests
10.04 - 24hr heat run test
2.04 - Polarity Check
12.04 - EE 4hr run
13.04 - AUG- UPS test

Edit, attach file or add comment


Created by Main.BorisBellesia on 2007-03-15 - 19:18

SCT in UJ33 - 15th Mar.

PDF RAT_20070315.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint3x2007x03x15x18x46/RAT_20070315.pdf

EE sys IST

6.03 DONE 600A EE systems IST - DFBLC
12.03 DONE 600A EE systems IST - DFBAE
16.03 DONE 600A EE systems IST - DFBM
6.03 ON GOING 13kA EE systems IST - L7
13.03 DONE 13kA EE systems IST - R7
DFBLC
14.03 ON GOING 600A no EE PC – IST
15.03 ON GOING 600A-EE interlock tests
15.03 ON GOING 600A-EE PC - IST
DFBAE+120A UJ33L
20.03 - 600A no EE PC – IST
23.03 - 600A-EE Interlock tests
23.03 - 600A-EE powering
28.03 - 120A – powering
DFBMD - L&R
29.03 - 120A - DFBM - powering
29.03 - 600A-EE interlock tests
29.03 - 600A-EE powering
WARM-MAGN. PC+120A UJ33R
2.04 - 600A - Warm magnets
4.04 - 120A – powering
HEAT RUNS
5.04 - 8hr HEAT RUN
6.04 - CCC tests
10.04 - 24hr heat run test
2.04 - Polarity Check
12.04 - EE 4hr run
13.04 - AUG- UPS test

Edit, attach file or add comment


Created by Main.BorisBellesia on 2007-03-13 - 20:25

SCT in UJ33 - 13th Mar.

PDF RAT_20070313.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint3x2007x03x13x20x24/RAT_20070313.pdf

Comments:

Edit, attach file or add comment


Created by Main.BorisBellesia on 2007-03-08 - 11:47

SCT in UJ33 - 8th Mar.

PDF RAT_20070308.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint3x2007x03x08x11x39/RAT_20070308.pdf

PDF Rapport_de_visite_du_7_mars_2007_point_3.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint3x2007x03x08x11x39/Rapport_de_visite_du_7_mars_2007_point_3.pdf

Comments:

Edit, attach file or add comment


Created by Main.BorisBellesia on 2007-03-06 - 17:21

SCT in UJ33 - 6th Mar.

PDF UJ33.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint3x2007x03x06x17x18/UJ33.pdf

Attached file contains:

  • Short Circuit Test Schedule

  • UJ33 Area divided with respect to the concerned circuits

  • Circuits names

Edit, attach file or add comment

Edit | Attach | Watch | Print version | History: r1 | Backlinks | Raw View | WYSIWYG | More topic actions
Topic revision: r1 - 2007-01-09 - JacekSzkutnik
 
    • Cern Search Icon Cern Search
    • TWiki Search Icon TWiki Search
    • Google Search Icon Google Search

    HCC All webs login