Created by Main.MikeKoratzinos on 2007-04-13 - 16:15

RAT meeting 13/4/2007

PowerPoint ICC_070413.ppt:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint8x2007x04x13x16x11/ICC_070413.ppt

PDF RAT_20070413.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint8x2007x04x13x16x11/RAT_20070413.pdf

Comments:

Edit, attach file or add comment


Created by Main.MirkoPojer on 2007-04-13 - 15:29

Beam Dump System Commissioning - RAT of April 10, 2007.

Comments: PLANNED INTERVENTIONS IN THE AREA

  • The bake-out of the whole MKDs-to-MKDs sector will be completed by w28.
  • A cabling campaign (including fire detection system) is foreseen for w16 to w19.
  • A water maintenance intervention has been scheduled for the w18 to w20 (demineralised water, cryogenic services and iced water will be affected).
  • Test of the MSD foreseen for w.21-22.
  • Cool-down of sector 5-6 for mid August.
  • Cool-down of sector 6-7 for mid October.
Open Issues
  • 10.04 Installation of BPMSD AB/BI
  • 10.04 Installation of BCTFD AB/BI
  • 10.04 Modifications on PDC of MKB-67 requested by Norisko AB/BT
  • 10.04 Mounting and alignment of beam dump line in RA63 AT/VAC
  • 10.04 Installation of MKD magnets in RA63 AB/BT
  • 10.04 Installation of junction modules between MKDs in RA67 AT/VAC
  • 03.04 Inspection by Norisko on PDC of UA63
  • 03.04 Assembly of PDC for MKDs in UA63 AB/BT
  • 03.04 Assembly of PDC for MKDs in UA67 AB/BT
  • 20.03 Mismatch between TCDS and MSD AT/VAC&AB/BT
  • 13.03 Grounding of instrumentation/after deconsignation AB/BT
  • 27.02 TCS: installation after dump line
  • 27.02 Vacuum tube between carbon window and TDE AB/ATB
  • 27.02 VMTAB bellows are needed for w18 AB/BT
  • 20.02 VAC: bake-out of 6L AT/VAC
  • 20.02 VAC: bake-out of 6R AT/VAC
  • 20.02 TDE in UD68 ready for end of June
  • 20.02 BPM installation AB/BI
  • 20.02 Vacuum pipe on Q4 AT/VAC-AB/BT
  • 20.02 Safety inspection by Norisko on PDC for MKD63 and MKB63
  • 20.02 Optical fibers for pulsing K. Loukili-TS/EL
Closed Issues
  • 10.04 Beam dump line in TD62 10.04
  • 10.04 BLMs integration 13.03
  • 10.04 Smoothing of the MSD 10.04
  • 03.04 Assembly of PDC for MKBs in UA63 03.04
  • 27.03 Safety inspection by Norisko on power distr.rack (MKB67) 20.02
  • 27.03 Grounding of instrumentation/before deconsignation 13.03
  • 10.04 Mounting supports for second beam (on drawings) (6L&R) 13.03
  • 27.03 Place for storing MKDs in UX65 20.03
  • 20.03 Grounding of magnets 13.03
  • 13.03 Intermediate bellows availability 27.02
  • 13.03 Interference between vacuum support and MKD 27.02
  • 27.02 Space in UJ62 and UJ67 for installation of spare TDE (and transport equipment) – late installation of that part of dump line 20.02

-- Main.MirkoPojer - 13 Apr 2007

Edit, attach file or add comment


Created by Main.BorisBellesia on 2007-04-13 - 15:28

SCT in UJ33 - 12th April

PDF RAT_20071204.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint3x2007x04x13x15x22/RAT_20071204.pdf

PDF SOC_settings_8hrun_UJ33.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint3x2007x04x13x15x22/SOC_settings_8hrun_UJ33.pdf

********************************** **********************************

1 - TS-CV confirmed that the ED circuit of the sector 2-3 will be normally operated the 16th-17th and the 19th.

********************************** **********************************

2 - In attachment: the current of each PC in UJ33 in the 4 steps of the 8hr run.

* HEAT RUNS Schedule:

22.03 DONE Polarity Check
30.03 DONE CCC tests: preparation for the 8hr run
16.04 - First 8hr HEAT RUN ; re-scheduled
17.04 - Second 8hr HEAT RUN
18.04 - CCC tests: preparation for the 24hr run
19.04 - 24hr HEAT RUN
20.04 - AUG - UPS test
21.05 - EE 4hr run