Created by Main.BorisBellesia on 2006-12-06 - 20:51
Advancement of today:
- AB-PO performed its tests on C34_L8 - C34-32_R7 - C12-14_R7 Problems on converters on C34_L8 and C12_R7 - location to be re-visited
- AB-PO/Polarity tests on 120A in RR77; circuits checked: RCBCH6, RCBCH7, RCBCH8, RCBCH9, RCBCH10 RCBCV6, RCBCV7, RCBCV8, RCBCV9, RCBCV10; Problems on the converters of the circuits RCBCH6 ,RCBCV6, RCBCV7 and RCBCH10, location to be re-visited
- Polarity tests on C26-28_L8
- TS-MME activities on C18-20-22-24-26_L8
Tomorrow activities:
- AB-PO activities on cells C34_L8 - C12_R7 - C16-20_R7 no problems for co activities.
- Polarity tests on C6-7-10_R7 no problems for co activities.
- TS-MME activities on C6-7-8-9-10_R7 co activities may be problematic with BLM/BPM
Information:
- 4 hr run of a set of converters foreseen for Friday
Edit, attach file or add comment
Created by Main.MircoCoccoli on 2006-12-06 - 15:17

RAT_20061206_wslides_wList.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint8x2006x12x06x15x14/RAT_20061206_wslides_wList.pdf
Comments:
AC non-conformity
- 13.11.06 Non-conformity of the crates of cryo instrumentation (inrush current) (A.Suraci: ready next year)
- 13.11.06 Non-conformity of the AC cabling of the crates under the magnets. This concerns ACR, MEL, orbit corrector power converters & VAC.
DC cabling
- 30.11.06 Non conformity: 6 temperature sensor cables need repair (D.Bozzini, A.Suraci)
- 25.11.06 Functional test on the leads heaters: DFBAO, DFBMA, DFBMC, DFBXG
- 22.11.06 Pre-connection of 120A cables in LSSR7 (TS/EL)
- 20.11.06 Galvanic insulation installation on all DFBs (AT/MEL)
- 13.11.06 6 kA and 13 kA cables positioning at DFBAO, DFBMA, DFBMC (Flohe)
Vacuum
-
Cryogenics
- 22.11.06 Cryo-valves remote control in CCC by AB/CO
- 22.11.06 Control of quench valve
DFB Commissioning
- 04.12.06 Re-positioning collars used to fix the WRL to the CLs (all DFBs) (A.Perin-D.Bozzini-F.Millet)
- 29.11.06 Pumping of Current Leads insulation vacuum for DFBX
- 13.11.06 ElQA-TP4-A for all DFBs between 7 and 8 (D.Bozzini: next(w48): DFBAO HC module, DFBMA, DFBMC, DFBX))
Safety
General remark: written communication in advance to announce operations!!!
- 25.11.06 ElQA-TP4B safety procedure (1900 volts tests!).
- 23.11.06 Wooden structure for UA access restriction (that will allow transport).
- 23.11.06 Preparation of a prototype insulating protection (derived from a plastic tube) of the monorail by J-C.Guillaume and approval by J.Etheridge.
- 23.11.06 Water leak on the tunnel concrete wall to be fixed (C33L8).
- 16.11.06 Cool down safety procedure & access conditions
Preparation of powering test
- 30.11.06 El_QA performed on C16L8. ICC test showed reversed sequence of V-taps on circuit RCBV16.L8B1. To be discussed on next RAT.
- 22.11.06 Installation of flexible cables by CV (UA83)
- 16.11.06 Water circulating in UA83 for the Powering Procedure Test: filters need to be checked.
AOB
- 13.11.06 BPM connection in Q2, Q3, Q4, Q5, Q6, Q7–wk49 (J-C.Guillaume & R.Jones)
Main.MircoCoccoli - 06 Dec 2006 - 15:16
Edit, attach file or add comment
Created by Main.MirkoPojer on 2006-12-06 - 12:47

RAT_20061206.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint5x2006x12x06x12x42/RAT_20061206.pdf
Comments: 8-H HEAT RUN ON GOING
Next meeting: Thursday, 7 at 8.30 in CCC.
Open Issues
- 22.11 Fire detection – awaiting certification
- 01.12 Short cables on 13 kA EE to be changed later on (temporary solution in place)
Heat Runs and Test Schedule
- 07.12 Fire detection test
- 08.12 Full power ventilation tests in RR57 – from 8:30 till 12:00
- 11.12 10am: 24-h heat run
- 12.12 UPS test.
- 13.12 Electric cut (AUG simulation).
- 13.12 Polarity Test
- 14.12 13kA energy extraction test.