Created by Main.MircoCoccoli on 2007-01-15 - 18:42

RAT_20070115.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint8x2007x01x15x18x38/RAT_20070115.pdf
MircoCoccoli - 15 Jan 2007 - 18:40
Open Issues:
AC non-conformity
- 13.11.06 Non-conformity of the crates of cryo instrumentation (inrush current) (A.Suraci: ready next year)
- 13.11.06 Non-conformity of the AC cabling of the crates under the magnets. This concerns ACR, MEL & VAC.
DC cabling
- 22.11.06 Pre-connection of 120A cables in LSSR7 (TS/EL) – PC Non conformities (H.Thiesen)
Instrumentation Cabling
- 12.01.07 Cryo-instrumentation cables: 2 LSS8L connectors (A.Suraci-J-C.Guillaume)
- 10.01.07 Continuity error with cable 1813004A and a wrong housing of 1702440 which should be replaced (D.Bozzini)
Cryogenics
- 22.11.06 Instrumentation and remote control not fully stable (P.Gayet - F.Millet)
Safety
General remark: written communication in advance to announce operations!!!
- 23.11.06 Water leak on the tunnel concrete wall to be fixed (C33L8).
Preparation of powering test
- 30.11.06 El_QA performed on C16L8. ICC test showed reversed sequence of V-taps on circuit RCBV16.L8B1 (D.Bozzini)
AOB
- 08.01.07 Re-installation of 3 BLMs interfering with pumping groups (B.Dehning)
- 13.11.06 BPM connection in Q2 (R.Jones) – waiting for Inner Triplet to be repaired
Edit, attach file or add comment
Created by Main.MirkoPojer on 2007-01-15 - 11:21

RAT_20070115.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint6x2007x01x15x11x07/RAT_20070115.pdf
Open Issues:
- 15.01 Loosen bolts on RCBYH4.R6B1 and RCBYV4.R6B2 PCs.
- 12.01 Power cut in ERD-R13
- 12.01 Cleaning of filters by CV (planned for 17.01)
- 10.01 QPS racks connection
- 21.12 Aluminum panel for the cables ducts/ shipping and install.
- 21.12 HV Insulation test of the DQS poles
Heat Runs and Test Schedule:
- 08.01 600A and 13 kA EE system IST. ON GOING
- 08.01 RB IST. ON GOING
- 11.01 120A powering tests. COMPLETED
- 15.01 2 kA powering tests. ON GOING
- 17.01 PIC-PC-QPS Interface tests.
- 19.01 600A powering tests. COMPLETED
- 23.01 600A-EE powering tests.
- 26.01 120A-600A-2kA 8h heat run.
- 30.01 RQD&F powering tests.
- 02.02 RB powering tests.
- 07.02 RQ&RB 8h heat run.
- 12.02 24h heat run test.
- 14.02 AUG&UPS test.
- 14.02 Polarity test.
- Main.MirkoPojer - 15 Jan 2007 - 11:15