TWiki home Point 1 Point 2 Point 3 Point 4 Point 5 Point 6 Point 7 Point 8 Minutes


Created by Main.MircoCoccoli on 2007-01-17 - 17:24

RAT in point 8 - 17th January - Minutes

PDF RAT_20070117_with_NC_Mag_Planning.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint8x2007x01x17x17x17/RAT_20070117_with_NC_Mag_Planning.pdf

> ATTENTION: next RAT in point 8 on FRIDAY 19th at 8.30am <

Edit, attach file or add comment


Created by Main.MircoCoccoli on 2007-01-17 - 16:43

Minutes of the meeting on Point 8 Warm Magnets Commissioning - 15th Jan

PDF Minutes_WarmMag_LSS8_15Jan07.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint8x2007x01x17x15x56/Minutes_WarmMag_LSS8_15Jan07.pdf

Edit, attach file or add comment


Created by Main.BorisBellesia on 2007-01-17 - 11:24

SCT_UA 67- UJ 67, Jan. 17th 2007

PDF RAT_20070117.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint6x2007x01x17x11x19/RAT_20070117.pdf

Open Issues

  • 17.01 Broken thermostat on 13 kA EE
  • 12.01 Power cut in ERD-R13
  • 12.01 Cleaning of filters by CV (planned for 17.01)
  • 10.01 QPS racks connection
  • 08.01 EE fan rotation problem – all ring
  • 21.12 Aluminum panel for the cables ducts/ shipping and install.
  • 21.12 HV Insulation test of the DQS poles

Heat Runs and Test Schedule

08.01 ON GOING 600A and 13 kA EE system IST
08.01 ON GOING RB IST
11.01 DONE 120A powering tests.
15.01 DONE 2 kA powering tests.
17.01 ON GOING PIC-PC-QPS Interface tests.
19.01 DONE 600A powering tests.
23.01 - 600A-EE powering tests.
26.01 - 120A-600A-2kA 8h heat run.
30.01 - RQD&F powering tests.
02.02 - RB powering tests.
07.02 - RQ&RB 8h heat run.
12.02 - 24h heat run test.
14.02 - AUG&UPS test.
14.02 - Polarity test.

Edit, attach file or add comment

Edit | Attach | Watch | Print version | History: r1 | Backlinks | Raw View | WYSIWYG | More topic actions
Topic revision: r1 - 2007-01-08 - JacekSzkutnik
 
    • Cern Search Icon Cern Search
    • TWiki Search Icon TWiki Search
    • Google Search Icon Google Search

    HCC All webs login