Created by Main.MircoCoccoli on 2007-01-17 - 17:24
> ATTENTION: next RAT in point 8 on FRIDAY 19th at 8.30am <
Edit, attach file or add comment
Created by Main.MircoCoccoli on 2007-01-17 - 16:43
Edit, attach file or add comment
Created by Main.BorisBellesia on 2007-01-17 - 11:24
08.01 | ON GOING | 600A and 13 kA EE system IST |
08.01 | ON GOING | RB IST |
11.01 | DONE | 120A powering tests. |
15.01 | DONE | 2 kA powering tests. |
17.01 | ON GOING | PIC-PC-QPS Interface tests. |
19.01 | DONE | 600A powering tests. |
23.01 | - | 600A-EE powering tests. |
26.01 | - | 120A-600A-2kA 8h heat run. |
30.01 | - | RQD&F powering tests. |
02.02 | - | RB powering tests. |
07.02 | - | RQ&RB 8h heat run. |
12.02 | - | 24h heat run test. |
14.02 | - | AUG&UPS test. |
14.02 | - | Polarity test. |