08.01 | DONE | 600A and 13 kA EE system IST. |
08.01 | DONE | RB IST. ON GOING |
11.01 | DONE | 120A powering tests. |
15.01 | DONE | 2 kA powering tests. |
15.01 | DONE | 600A powering tests. |
17.01 | DONE | 600A-EE powering tests. |
22.01 | - | PIC-PC-QPS Interface tests. |
23.01 | - | RQD&F powering tests. |
24.01 | - | RB powering tests. |
26.01 | - | 120A-600A-2kA-RQD/F-RB 8h heat run. |
05.02 | - | 24h heat run test. |
07.02 | - | Polarity test. |
14.02 | - | AUG&UPS test. |