Created by Main.MatteoSolfaroli on 2007-06-12 - 18:25
Test Report of Tuesday 12.06.2007
- ElQA
- Tests in MBA line will continue tomorrow till noon.
- RD2.L8:
- Ramped to 200A. Quench heater fired. Post-mortem data acquired properly. Test OK
- Ramped to 1kA. Quench heater fired. Post-mortem data does not arrive properly to the viewer. Test NOT OK
- Second ramp to 1kA. Quench heater fired. Post-mortem data created is corrupted: the data is an exact copy of the one created in the previous with no new data. The QPS controller needs to be restarted. Test NOT OK
- 600A QPS Controllers:
- RQ6.R7B1 and RQ6.R7B2 are now ready for powering. Next step: PCS.4 (plateau at 200A)
- The available 600A correctors in the DFBAO are released by AT/MEL for powering.
- Sequencer Test 600A sequence - Completed using RQTL12.L8B2
- RQ6.R7:
- Different ramp rate applied (up to nominal ramp rate of 1.3 A/s). Current cycles between +10A -10A.
- Noise level: 20 mV
- Circuit ramped at 5 A/s: trip at 20A. Test NOT OK.
Planning for Wednesday 13.06.2007
- AM
- ELQA Test of MBA line will continue till 14h00.
- RQ6.R7B1 and RQ6.R7B2: Repair of the cable
- PM (14:00 in CCC)
- RQ6.R7B1 and RQ6.R7B2: Repeat test
- 600 A circuits of L8: PCC (<20A) for all
- 600 A circuits of L8: PIC2 for all
- 600 A circuits of L8:PCS.1 for all
- QPS IST RQF.A78 and RQD.A78
- Quench heater charge/discharge RQF and RQD circuits
- RD2.L8, RQ4.L8 and RQ5.L8 and their correctors: Powering possible once Reiner has solved the problem with the PM data generation
- AB/PO Type tests on 60A converter
- In the late afternoon: ElQA on the 600A circuits of DFBAN.
- List of the 600A circuits released by AT/MEL and AT/ACR
-
- RQTL12.L8B1
- RQTF.A78B1
- RQTF.A78B2
- RSD1.A78B1
- RQS.L8B1
- RSD2.A78B1
- RSD2.A78B2
- RSF1.A78B1
- RSF1.A78B2
- RCO.A78B1