Created by Main.BorisBellesia on 2007-03-23 - 17:22

SCT in UJ33 - 23th March

PDF RAT_20070323.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint3x2007x03x23x17x16/RAT_20070323.pdf

PDF Etude-sect-cablesDC-UJ33-tot.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint3x2007x03x23x17x16/Etude-sect-cablesDC-UJ33-tot.pdf

ATTACHED: Machine Profile for the 8hr run in UJ33: Power Converters Utilization Factors

EE sys IST

6.03 DONE 600A EE systems IST - DFBLC
12.03 DONE 600A EE systems IST - DFBAE
16.03 DONE 600A EE systems IST - DFBM
6.03 DONE 13kA EE systems IST - L7
13.03 DONE 13kA EE systems IST - R7
DFBLC
14.03 DONE 600A no EE PC – IST
15.03 DONE 600A-EE interlock tests
15.03 DONE 600A-EE PC - IST
DFBAE+120A UJ33L
20.03 DONE 600A no EE PC; IST
23.03 DONE 600A-EE Interlock tests
23.03 DONE 600A-EE powering
28.03 DONE 120A; powering
DFBMD - L&R
29.03 DONE 120A - DFBM - powering
29.03 DONE 600A-EE interlock tests
29.03 DONE 600A-EE powering
WARM-MAGN. PC+120A UJ33R
2.04 DONE 600A - Warm magnets
4.04 DONE 120A 1; powering
HEAT RUNS
5.04 - 8hr HEAT RUN
6.04 - CCC tests
10.04 - 24hr heat run test
2.04 - Polarity Check
12.04 - EE 4hr run
13.04 - AUG- UPS test

Edit, attach file or add comment


Created by Main.MikeKoratzinos on 2007-03-23 - 15:46

RAT meeting 23/3/2007

PDF RAT_20070323.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint8x2007x03x23x15x45/RAT_20070323.pdf

Comments:

Edit, attach file or add comment


Created by Main.MirkoPojer on 2007-03-23 - 09:55

Beam Dump System Commissioning - RAT of March 20, 2007.

PDF RAT_20070320.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint6x2007x03x23x09x40/RAT_20070320.pdf

Planned interventions in the area

  • Smoothing of the MSD is foreseen for this week (w.12).
  • A campaign for fire detection system cabling is foreseen for w14 to w17.
  • A water maintenance intervention has been scheduled for the w18 to w20 (demineralised water, cryogenic services and iced water will be affected).
  • Test of the MSD foreseen for w.21-22.
  • Cool-down of sector 5-6 for mid August.
  • Cool-down of sector 6-7 for mid October.
Open Issues
  • 20.03 Mismatch between TCDS and MSD AT/VAC&AB/BT
  • 20.03 Place for storing MKDs in UX65 AB/BT
  • 13.03 Mounting supports for second beam (on drawings) AB/BT
  • 13.03 BLMs integration AB/BT&ICL
  • 13.03 Grounding of instrumentation AB/BT
  • 27.02 TCS: installation after dump line
  • 27.02 Vacuum tube between carbon window and TDE AB/ATB
  • 27.02 VMTAB bellows are needed for w18 AB/BT
  • 20.02 VAC: bake-out of 6L by w-13 AT/VAC
  • 20.02 VAC: bake-out of 6R by w-15 AT/VAC
  • 20.02 TDE in UD68 ready for end of June
  • 20.02 BPM installation AB/BI
  • 20.02 Vacuum pipe on Q4 AT/VAC-AB/BT
  • 20.02 Safety inspection by Norisko on power distr. racks
  • 20.02 Optical fibers for pulsing (compl. W11) K. Loukili-TS/EL
Closed Issues
  • 20.03 Grounding of magnets 13.03
  • 13.03 Intermediate bellows availability 27.02
  • 13.03 Interference between vacuum support and MKD L. Ducimetiere 27.02
  • 27.02 Space in UJ62 and UJ67 for installation of spare TDE (and transport equipment) – late installation of that part of dump line 20.02

Edit, attach file or add comment

Edit | Attach | Watch | Print version | History: r2 < r1 | Backlinks | Raw View | WYSIWYG | More topic actions