TWiki home | Point 1 | Point 2 | Point 3 | Point 4 | Point 5 | Point 6 | Point 7 | Point 8 | Minutes |
Created by Main.MariaPazCasasLino on 2007-05-16 - 17:38
13kA EE | DONE | 16-04-07 |
600A EE | DONE | 23-04-07 |
Circuits >2kA | ||
Powering tests PC 4-8kA | ON GOING | 09-05-07 |
8h run 4-8kA | - | 24-05-07 |
Interlock tests RQD&F | - | 22-05-07 |
Powering tests RQD&F | - | 23-05-07 |
Preparation RB.A23 | ON GOING | 19-04-07 |
Interlock tests RB.A23 | - | 29-05-07 |
Powering tests RB.A23 | - | 30-05-07 |
8h run >= 8kA | - | 04-06-07 |
Pic interface test | - | 16-06-07 |
Circuits < 2kA | ||
120A powering tests | DONE | 03-05-07 |
600ANOEE powering tests | ON GOING | 08-05-07 |
600A-EE interlock tests | - | 22-05-07 |
600A-EE powering tests | DONE | 08-05-07 |
8 hr run PC < 2kA | - | 24-05-07 |
24hr heat run test | - | 07-06-07 |
Polarity test < 8KA | - | 25-05-07 |
Polarity Check > 8KA | - | 05-06-07 |
AUG- UPS test | - | 08-06-07 |
Edit, attach file or add comment
Created by Main.MariaPazCasasLino on 2007-05-16 - 17:02
Edit, attach file or add comment
Created by Main.MariaPazCasasLino on 2007-05-16 - 15:50
Edit, attach file or add comment
Created by Main.BorisBellesia on 2007-05-16 - 12:25
14:00 | PCC for Q5 |
15:00 | PIC2 for D2,Q4,Q5: Ivan and Boris from the CCC, the rest in the FCC If things go smoothly |
16:00 | Start P2N, preferably Q5, final decision around 15:00. In the sequence a quench at 1000A will be provoked (if we reach this far) |