Created by Main.MirkoPojer on 2007-05-23 - 19:02

Powering Tests of Sector 7-8: activity of Wednesday 23/05.

Today the activity was concentrated on Q5, which was released by MPP after analysis of the quench of Monday morning.

The following tests have been executed on Q5 (MANUAL execution):
  • ramp to nominal (4310 A) with 5 A/s ramp rate: quenched occurred at 4210 A on B2 aperture; preliminary analysis confirmed it was a training quench;
  • ramp to nominal (4310 A) with 5 A/s ramp rate: NO quench; a plateau of 10 min was mantained for possible voltage drift recording;
  • keeping B1 power converter at nominal current, B2 power converter was lowered to 55% of the nominal current (2370 A); with this unbalanced configuration, a quench was driven by QPS generating an artificial quench signal from one current lead detector; test was successful;
  • ramp to nominal (4310 A) with 5 A/s ramp rate: NO quench; a FPA was provoked from power converter, with an apparently too high ramp rate which triggered the quench detector.

Proposal for the activity of tomorrow.

Q4 and D2 will be tested from CCC.

Works towards powering the main circuits in the arc and the 600 A correctors (before reaching 1.9 K):

  • plastic bags on 600 A leads (action S. Kockorowski);
  • IST of QPS for which 1.9 K is not required (action R. Denz);
Once 1.9 K are reached:
  • ElQA for the three 13 kA circuits and some selected 600 A correctors (list to be provided by HCC; action D. Bozzini);
  • IST of QPS at 1.9 K (action R. Denz);
  • OK from PIC, PC, EE and Current Leads.

Edit, attach file or add comment


Created by Main.BorisBellesia on 2007-05-23 - 12:26

Short Circuit Tests in UA27 - 23rd May

PDF RAT_20070523.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint2x2007x05x23x12x21/RAT_20070523.pdf

Microsoft Excel Spreadsheet SOC_UA27_8hrheatrun.xls:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint2x2007x05x23x12x21/SOC_UA27_8hrheatrun.xls

  • The Set Of Circuits for the 8hr heat run attached. It includes all the circuits ion UA27 but the 13kA and the ones belonging to the powering subsector XR2

EE - IST    
13kA EE DONE 16-04-07
600A EE DONE 23-04-07
     
Circuits >2kA    
Powering tests PC 4-8kA - 11-05-07
8h run 4-8kA ON GOING 29-05-07
Interlock tests RQD&F ONGOING 02-05-07
Powering tests RQD&F - 24-05-07
Preparation RB.A23 ON GOING 19-04-07
Interlock tests RB.A23 - 29-05-07
Powering tests RB.A23 - 30-05-07
8h run >= 8kA - 04-06-07
     
Circuits < 2kA    
120A powering tests DONE 03-05-07
600ANOEE powering tests ON GOING 08-05-07
600A-EE interlock tests ON GOING 03-05-07
600A-EE powering tests DONE 18-05-07
8 hr run PC < 2kA - 29-05-07
     
24hr heat run test - 07-06-07
     
Polarity Check < 8KA - 30-05-07
AUG- UPS test - 08-06-07

Edit, attach file or add comment


Created by Main.AntonioVergara on 2007-05-23 - 12:01

Powering Tests Sector 78 - Minutes 23/05/2007

PDF RAT_20070524.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint8x2007x05x23x11x59/RAT_20070524.pdf

Comments:

Edit, attach file or add comment

Edit | Attach | Watch | Print version | History: r1 | Backlinks | Raw View | WYSIWYG | More topic actions
Topic revision: r1 - 2007-05-02 - JacekSzkutnik
 
    • Cern Search Icon Cern Search
    • TWiki Search Icon TWiki Search
    • Google Search Icon Google Search

    HCC All webs login