Powering Tests - Sector 7-8 - 30/05/2007

Yesterday was devoted to perform tests on RD2.L8 and RQ4.L8

    • RD2.L8 has been successfully commissioned up to PNO.8d (Current cycle up to nominal current)
    • Missing tests for RD2.L8: Fast Power Abort from PIC (PNO.9). The detection threshold needs to be modified. Possibly done while powering at unison (like PNO.9 for RQ5)
    • RQ4.L8:
        • Unbalanced cycle up to nominal (3610 A) for B1 and 2000 A for B2. While ramping B1 converter tripped. The attempt of PO expert to recover control made the quench detector trip (same problem as last week)
        • Second trial of unbalanced cycle up to nominal: with B1 at nominal current and B2 ramping up to nominal, the latter quenched at 3590 A. Test failed.

Proposal for the activity of today (30/05/2007)

  • Complete P2N of all the 120-80A correctors of Q4 and Q5.
  • Continue P2N of RQ4.L8. Two options: * Unbalanced ramp up and quench with both apertures at nominal current (PNO.7a) or/and * Unbalanced cycle and quench with one aperture at nominal and the other at 50%.

  • ElQA activities: Morning: * Full qualification of the 3 circuits selected on DFBAN * TFM on circuits powered via DFBMH * preparation for the HV qualification of the 600A circuits Afternoon * HV qualification on 600 A circuits powered via DFBAO

  • QPS: Interlock tests .

Comments:

Edit, attach file or add comment


Created by Main.BorisBellesia on 2007-05-29 - 11:12

Short Circuit Test UA27 - 29th May

PDF RAT_20070529.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint2x2007x05x29x11x06/RAT_20070529.pdf

**********************************

8hr heat run ON GONIG: all circuits belonging to the powering sub-sector MR2 and A23 (but 13kA)

**********************************

EE - IST    
13kA EE DONE 16-04-07
600A EE DONE 23-04-07
     
Circuits >2kA    
Powering tests PC 4-8kA DONE 11-05-07
8h run 4-8kA ONGOING 29-05-07
Interlock tests RQD&F ONGOING 30-05-07
Powering tests RQD&F - 30-05-07
Preparation RB.A23 DONE 19-04-07
Interlock tests RB.A23 DONE 25-05-07
Powering tests RB.A23 - 30-05-07
8h run >= 8kA - 04-06-07
     
Circuits < 2kA    
120A powering tests DONE 03-05-07
600ANOEE powering tests DONE 08-05-07
600A-EE interlock tests DONE 03-05-07
600A-EE powering tests DONE 18-05-07
8 hr run PC < 2kA ONGOING 29-05-07
     
24hr heat run test - 07-06-07
     
Polarity Check < 8KA - 30-05-07
AUG- UPS test - 08-06-07

Edit, attach file or add comment


Created by Main.BlancaPereaSolano on 2007-05-29 - 10:57

Powering Tests of Sector 7-8: minutes of the meetings of 29/05

PDF RAT_20070529.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint8x2007x05x29x10x56/RAT_20070529.pdf

Comments:

Edit, attach file or add comment

Edit | Attach | Watch | Print version | History: r1 | Backlinks | Raw View | WYSIWYG | More topic actions
Topic revision: r1 - 2007-05-02 - JacekSzkutnik
 
    • Cern Search Icon Cern Search
    • TWiki Search Icon TWiki Search
    • Google Search Icon Google Search

    HCC All webs login