Created by Main.MirkoPojer on 2006-11-17 - 16:54

Preparation of cool-down in sector 78, 17 Nov

PDF RAT_20061117.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint8x2006x11x17x16x48/RAT_20061117.pdf

Comments:

AC non-conformity

  • 13.11.06 Non-conformity of the crates of cryo instrumentation (inrush current)
  • 13.11.06 Non-conformity of the AC cabling of the crates under the magnets. This concerns ACR, MEL, orbit corrector power converetrs & VAC.
  • 13.11.06 Non-conformity of the DC cabling of the orbit corrector power converters
DC cabling
  • 13.11.06 6 kA and 13 kA cables positioning at DFBAO, DFBMA and DFBMC
  • 13.11.06 120 A cable connections in DFBAO, DFBMC, DFBMA and DFBX LSS8L
  • 17.11.06 600 A cable positioning on DFBA
Assembly -

Vacuum

  • 17.11.06 Leak in arc (Q11-8L)
  • 17.11.06 Bellows damaged in Q6-Q7 LSS8L
Cryogenics
  • 17.11.06 Instrumentation cable HV tests in LSS8L
  • 17.11.06 Cryogenic valve manipulation on DFBX
  • 17.11.06 Pressurized air supply to valve on WRL
  • 13.11.06 Support on DFBAO WRL
DFB Commissioning
  • 17.11.06 Prototype of galvanic insulation to be tested at Point 6
  • 13.11.06 ElQA-TP4-A in the DFBAO, DFBAN, DFBAX
  • 17.11.06 Pumping of insulation vacuum will start next week in 7R
Safety General remark: written communication in advance to announce operations!!!
  • 16.11.06 Cool down safety procedure & access conditions
  • 16.11.06 Definition of Safety procedure for Powering Procedure Test (aka Dry Runs)
  • 17.11.06 Monorail in Point 8 locked off on Monday starting from 10.30!!!
Preparation of powering test
  • 16.11.06 Water circulating in UA83 for the Powering Procedure Test: filters need to be cleaned!
AOB
  • 13.11.06 BPM connection in Q2, Q3, Q4, Q5, Q6, Q7
  • 13.11.06 Quench protection continuity tests and cables assignment LLS7R (DFBMH, DFBAN) and LSS8L (DFBMC, DFBMA and DFBX)

Edit, attach file or add comment


Created by Main.JacekSzkutnik on 2006-11-17 - 14:41

Essais en court-circuits UJ56 et RR57

Bonjour,

Les visites des installations électriques des ouvrages cités en objet ont été réalisées à ce jour. Aucune non conformité ne s'oppose à ce que les essais en court-circuit soient effectués à partir du 20 novembre 2006. Les rapports de visite parviendront ultérieurement aux responsables de chaque installation.

Cordialement,

Caroline BENOIT-GONIN Norisko Equipements pour SC/GS Office 57-2-024 caroline.benoit-gonin@cernNOSPAMPLEASE.ch

Comments:

Edit, attach file or add comment


Created by Main.RosarioPrincipe on 2006-11-17 - 12:09

Test on the DQSQD switch, today Friday Nov 17.

Please find enclose a small report of the tests held in UA63 concerning the 13kA switch DQSQD.

Regards

PDF RAT_20061117.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint6x2006x11x17x12x07/RAT_20061117.pdf

Comments:

Edit, attach file or add comment

Edit | Attach | Watch | Print version | History: r1 | Backlinks | Raw View | WYSIWYG | More topic actions
Topic revision: r1 - 2006-11-01 - JacekSzkutnik
 
    • Cern Search Icon Cern Search
    • TWiki Search Icon TWiki Search
    • Google Search Icon Google Search

    HCC All webs login