Created by Main.MirkoPojer on 2007-10-31 - 20:49

Installation and Commissioning of the Beam Dump System _ Minutes of 30/10/07 meeting

PDF RAT__20071030.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint6x2007x10x31x20x48/RAT__20071030.pdf

Comments:

Edit, attach file or add comment


Created by Main.BorisBellesia on 2007-10-31 - 10:40

From Pressure Test to Cooldown - Sectors 45 and 34 - 30th October

Pptx Sector45_34_status_20071030.pptx:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint4x2007x10x31x10x10/Sector45_34_status_20071030.pptx

Comments:

Edit, attach file or add comment


Created by Main.MirkoPojer on 2007-10-30 - 19:39

From Pressure Test to Cool-down _ Sector 6-7 _ 30/10/2007

JPEG 6-7_october30.jpg:
6-7_october30.jpg

Comments:

Edit, attach file or add comment


Created by Main.MirkoPojer on 2007-10-30 - 19:38

From Pressure Test to Cool-down _ Sector 5-6 _ 30/10/2007

JPEG 5-6_october30.jpg:
5-6_october30.jpg

Comments:

Edit, attach file or add comment


Created by Main.AntonioVergara on 2007-10-25 - 09:30

From Pressure Tests tp Cooldown - Sector 8-1 - Thursday October 25, 2007

Pptx Sector81_status_20071025.pptx:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint8x2007x10x25x08x43/Sector81_status_20071025.pptx

Sector 8-1

Going-on Activities

  • It has been decided to repair the flexibles in the DFBAs of Sector 8-1 before the global leak tests, allocated dates are:
    • DFBAP repair: Wk 44
    • DFBAA repair: Wk 45

  • SSS Interconnection

  • Inner Triplets:
    • Left 1: closed, being leak tested
    • Right 8: closed, being leak tested

  • Electrical non-conformities on instrumentation cables of the power converters will be closed by the end of the week.

  • The procedure for cleaning the DFBXH is currently being completed. Due to unavailabily of the person responsible to do the works, cleaning cannot start on week 45 as expected but will have to be postponed till 46.

Planned activities

  • PIC-PC interface test - Wk 45
  • Room temperature vacuum and collimator works (wks 43-46), bake-out (wks 47 -48)
  • ATLAS-RP cable installation - Wks 48-49
  • TS/EL:
    • New water-cooled cable DFBXH: Wk 45 - Saturday & Wk 46
    • Replacement of water-cooled cable of RQ6 in the DFBAP - Wk 44
    • Week 46: Presentation of the cables and installation of the cable supports on the DFBMs in RA83.
  • ElQA
    • TP4-A: Inner triplet L1 - Week 46
    • TP4-A: Inner triplet R8 - Week 46

General

  • Cooling water shut-down - Wks 42-44 - All the cryogeninc activities will be stopped.

Comments:

Edit, attach file or add comment


Created by Main.BorisBellesia on 2007-10-23 - 12:24

From pressure test to Cooldown - Sector45 and 34 - 23rd October

Pptx Sector45_34_status_20071023.pptx:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint4x2007x10x23x12x22/Sector45_34_status_20071023.pptx

Comments:

Edit, attach file or add comment


Created by Main.BorisBellesia on 2007-10-23 - 12:21

From pressure test to cooldown - 23rd October 2007

Comments:

Edit, attach file or add comment


Created by Main.BorisBellesia on 2007-10-23 - 12:15

Preparation for cooldown - RF-Powering tests-Installation activities

PDF RAT_20071022.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint4x2007x10x23x12x14/RAT_20071022.pdf

PowerPoint Sector45_34_RF-PT_planning.ppt:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint4x2007x10x23x12x14/Sector45_34_RF-PT_planning.ppt

Comments:

Edit, attach file or add comment


Created by Main.AntonioVergara on 2007-10-22 - 16:27

From the Pressure Tests to the Cooldown - Sector 8-1 - October 19, 2007

Sector 8-1

Going-on Activities

  • SSS Replacement

  • Inner Triplets:
    • Left 1: closed, being leak tested
    • Right 8: closed, being leak tested

  • Electrical non-conformities on instrumentation cables of the power converters will be closed by the end of the week.

  • The procedure for cleaning the DFBXH is currently being completed. In principle, the instrumentation wont have to be removed.

Planned activities

  • PIC-PC interface test - Wk 43
  • Room temperature vacuum and collimator works (wks 43-46), bake-out (wks 47 -48)
  • ATLAS-RP cable installation - Wks 48-49
  • TS/EL:
    • DFBXH Ineo cabling - To be done on Monday 22.
    • Installation of the removed water-cooled cable and RQ6 - Flohe Wk 44 - 45 Once the cleaning is completed.
    • NC DFBXH: The water cooled cable associated to the current lead #3 cannot be fixed to the lead on the left side. There is a mechanical interference between the water tube on the lug and a connector necessary for the routing of the protection signal from the intrumentation port. The connector cannot be moved to another position, it is therefore proposed to fix the water cooled cable on the right side of the current lead lug.
  • ElQA
    • TP4-A: Inner triplet L1 - as soon as possible since it will be the first time they are performed
    • TP4-A: Inner triplet R8 - not before the DFBX is repaired
  • Alarm test in the whole sector will be carried out on Wednesday 24.

General

  • Cooling water shut-down - Wks 42-44 - All the cryogeninc activities will be stopped.
  • A latest date for taking a decission about repairing or not the DFBAs has to be set for not jeopardizing the starting date of the flushing

Comments:

Edit, attach file or add comment


Created by Main.MirkoPojer on 2007-10-17 - 23:15

From pressure test to cool-down - Sector 5-6 - 16/10/07

JPEG Sector_5-6_status_161007.jpg:
Sector_5-6_status_161007.jpg

Comments:

Edit, attach file or add comment


Created by Main.AntonioVergara on 2007-10-17 - 17:02

From Pressure Tests to Cooldown - Sector 81 - October 16, 2007

Sector 8-1

Going-on Activities

  • SSS Replacement

  • Inner Triplets:
    • Left 1: closed, being leak tested
    • Right 8: closed, being leak tested

  • Electrical non-conformities on instrumentation cables of the power converters will be closed by the end of the week.

Planned activities

  • PIC-PC interface test - Wk 43
  • Room temperature vacuum and collimator works (wks 43-46), bake-out (wks 47 -48)
  • ATLAS-RP cable installation - Wks 48-49
  • DFBXH:
    • Ineo cabling - Wk 43
    • Installation of the removed water-cooled cable and RQ6 - Flohe Wk 45
    • New cleaning of the DFBXH, the instrumentation will have to be removed and the DFBX re-validated by AT-MEL afterwards - Wk ?
  • ElQA
    • TP4-A: Inner triplet L1 - as soon as possible since it will be the first time they are performed
    • TP4-A: Inner triplet R8 - not before the DFBX is repaired

General

  • AUG test on October 19
  • Cooling water shut-down - Wks 42-44 - All the cryogeninc activities will be stopped.
  • A latest date for taking a decission about repairing or not the DFBAs has to be set for not jeopardizing the starting date of the flushing

Comments:

Edit, attach file or add comment


Created by Main.MariaPazCasasLino on 2007-10-16 - 18:05

Warm Magnets Commissioning Point 2 and 4. Minutes 16-10-2007

PDF RAT_20071016_WM2-4.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint2x2007x10x16x18x03/RAT_20071016_WM2-4.pdf

Comments:

Edit, attach file or add comment


Created by Main.BorisBellesia on 2007-10-16 - 16:06

From Pressure test to Cooldown - 16th October - Point4

Pptx Sector45_34_status_20071015.pptx:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint4x2007x10x16x15x57/Sector45_34_status_20071015.pptx

Sectors 45 and 34

  • Minutes: see attached presentation

  • Sector34 Open Issue: Needed strict coordination among AT-MCS, AT-VAC and AT-ACR to define priorities of DSL interconnection and 7L3 leaks localization/repair. A. Perin is the expert to who address technical questions.

Edit, attach file or add comment


Created by Main.BorisBellesia on 2007-10-16 - 14:24

From Pressure test to CooLdown - 16th Oct.

Comments:

Edit, attach file or add comment


Created by Main.AntonioVergara on 2007-10-11 - 09:34

From Pressure Tests to Cooldown - Point 8 - Thursday Oct 11, 2007

Sector 8-1

Going-on Activities

  • SSS Replacement, including:
    • Replacement and interconnection works
    • Leak tests
    • Local ElQA tests

  • Inner Triplets:
    • Left 1: closed, being leak tested
    • Right 8: leak localised in C'. Repair going on. Final test wil be done once the SSS repairs are finished.

  • Electrical non-conformities on instrumentation cables of the power converters will be closed by the end of the week.

  • LHCb compensator tests will last till tomorrow Friday

  • Installation of the instrumentation rods in DFBs Right 8 - COMPLETED

  • Water pump check Point 8 planned for this week

Planned activities

  • PIC-PC interface test - Wk 43
  • Room temperature vacuum and collimator works (wks 43-46), bake-out (wks 47 -48)
  • ATLAS-RP cable installation - Wks 48-49
  • DFBXH:
    • Ineo cabling - Wk 43
    • Installation of the removed water-cooled cable - Flohe Wk ?
    • New cleaning of the DFBXH, the instrumentation will have to be removed and the DFBX re-validated by AT-MEL afterwards - Wk ?
  • MB1158 diode: electrical continuity tests - Monday 15 Oct
  • Flexible water cable reconnection DFBs Left 1 - Week 42

General

  • AUG test on October 19 - Real impact will be described today
  • Cooling water shut-down - Wks 42-44 - All the cryogeninc activities will be stopped. The purging acitivities required to continue with he vacuum tests could be carried out using a temporary solution. Paul will ask Francois to go ahead with it.
  • A latest date for taking a decission about repairing or not the DFBAs has to be set for not jeopardizing the starting date of the flushing

Comments:

Edit, attach file or add comment


Created by Main.MariaPazCasasLino on 2007-10-10 - 20:21

Warm Magnets Commissioning Point 4. Minutes 09-10-2007

PDF Warm_Magnets_Point4_Minutes.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint4x2007x10x10x20x20/Warm_Magnets_Point4_Minutes.pdf

Comments:

Edit, attach file or add comment


Created by Main.MirkoPojer on 2007-10-09 - 21:28

From Pressure test to Cool-down - Sector 5-6 _ 09/10/2007

JPEG 5-6.jpg:
5-6.jpg

Feedback of the meeting:

  • Problems with the soldering of the flexible of DFBAJ - To be resolded (after meeting: soldered, waiting for radiography)
  • ElQA on DFBXF.3R5 not yet done (after meeting: possibly done on Thursday)
  • Cool-down could be delayed 1 week (start on w.46)

After meeting:

  • Partial coherence test successfully performed
  • Leak in 15L6 will be repaired on Wednesday; 3 bars will be put during night to check
  • Rail for re-routing of 120 A cables on DFBLE.RR57 is in place; connection on Wednesday

Edit, attach file or add comment


Created by Main.BorisBellesia on 2007-10-09 - 20:16

From Pressure Test to Cool-Down - Tuesday 09 - Point 4

SECTOR45

General planning:

  • W41-W42: L5 to 80K
  • W42-W43: Cool-down of the whole sector from 80K up to 4.5K
  • W44: Cool-down of the arc45 from 4.5K up to 1.9K / ElQA of the Circuits of the matching sections / Powering tests of the matching sections
  • W45: ElQA of the circuits of the arc and Powering tests of the matching sections
  • W46: Powering tests of the circuits of the arc

Activitites - w41:

  • Today -09/10 - cooldown L5 to 80K
    • Sector closed since 08/10
    • Access allowed with key and tokens except RE52-UL55
    • See document LHC-S-ES-0017 for particular access conditions
  • ElQA break-down monitoring all along cooldown; AT-MEL
  • QPS activities; AT-MEL
  • CMS vacuum installation/tests; AT-VAC
  • Magnet alignment; TS-SU
  • Cable campaign point5; TS-EL
  • Inner triplet interconnection; AT-MCS

Open Issues + Long term activitites:

  • Swapped cables of RB circuit on DFBA RR53
  • Cleaning – W43/44
  • Collimator installation W44
  • CMS-ZDC optical fiber installation; W44

SECTOR34

General planning+Activities:

  • W40: Pressure test of the arc / DSL still disconnected
  • W41-W42:
    • Consolidation
      • All lines under nominal pressure up to Wed. 10/10 - AT-VAC/ACR
      • Cryo-valves reconfiguration Thu.-Fri. 11-12/10 - AT-ACR
      • Opening and repairs of leaks (two leaks found: 7R4 ~2*10^-6 [mbar*l/s] and 7L4 ~10^-5 [mbar*l/s]) - AT-MCS/VAC
    • Checks the jacks - stable pressure conditions needed - 2 days needed - date to be decided, possibly on Friday 12/10 - TS-IC
    • ElQA.DOC from Wed. 10/10 - AT-MEL
    • Manometer installation on the ceiling at the level of RE38 – trolley passage difficult – TS-IC
  • W43: DFBLC-DSLC-DFBAF interconnections start (possibility to start during W42 if compatibility with consolidation)
  • W50: Flushing

Edit, attach file or add comment


Created by Main.AntonioVergara on 2007-10-09 - 11:51

From Pressure Tests to Cooldown - Point 8 - Monday 09.10.2007

Sector 8-1

  • Inner Triplets
    • Right 8: the leak has been located in line C', precisely on a weld in the middle of the flexible. It is currently being replaced by the US collaborators. Once it is corrected and the works in the SSS completed, the inner triplet will be pressurised again for testing. It should be sufficient for this test to have the C' line in the SSS welded, however it is not sure that only one line can be pressurised without affecting the other lines, hence most likely the test will be carried out at the end of the SSS works (wk 47).
    • Left 1: inner triplet closed and being leak-tested.
  • SSS Q17R8
    • The replacement of the SSS started this week and will last till wk 46.
    • Local electrical tests will progress in parallel with the assembly of the SSS.
  • MB1158
    • The diode has been cleaned up. A continuity test will be done before closure beginning of next week. The final validation cannot be done before the TP4-A before the flushing.
  • DFBAs repairs
    • A latest date for taking a decission about repairing or not the DFBAs has to be set for not jeopardizing the starting date of the flushing.
    • Paolo reminds that the time used for reparing the DFBAs will be different for each sector due to the different configurations.
  • ElQA
    • TP4-A is planned for week 47, just before the flushing.
    • Low voltage continuity tests of the dipole lines will be carried ut during the SSS replacement between the DFBAA and C18R8
    • The non-conformities being corrected by INEO this week will be re-checked once they are closed.
  • AUG Test
    • The yearly AUG test for the whole Point 8 is planned for October 19. HCC will study how can we get the maximum profit from it.
  • A4L1
    • Vacuum mechanical works will start on week 43 and will last till week 47.
    • Collimator to be installed week 44.
    • Neg-activation weeks 48 and 49 (overlaps with one week of flushing)
  • LHCb Compensator Magnet Tests
    • The three compensator magnets will be on today and tomorrow. No interference with other activities.
  • Cryogenics
    • Nothing pressurized in the cold circuits.
    • Warm helium line a few mbars above atm pressure
    • Installation of the instrumentation rods in the DFBs of Right 8 will be done tomorrow Wednesday

Comments:

Edit, attach file or add comment


Created by Main.MariaPazCasasLino on 2007-10-03 - 15:32

Warm Magnets Commissioning in point 6. Action list for the 24h run and polarity test

-Thursday 4th morning: Setup ongoing (Bernard Dubois) and pre-test from the CCC before 10:30h

-Thursday 4th,10:30h: Consignation of the converters in order to remove the covers from the magnets (Jacky Mazet)

-Thursday 4th,≈14:00h: Once the covers are removed, the converters will be deconsignée (Jacky Mazet)

-Thursday 4th,after deconsignation of the converters: Start of the 24h heat run from the CCC

-Thursday 4th,≈ 17:00h: General verification on the cables (Baptiste Lebeau)

-Friday 5th, before finishing the 24h heat run: Polarity test (Jacky Mazet)

-Friday 5th, ≈ 13:30h: Magnets and cables temperatures measurements (Jacky Mazet, Baptiste Lebeau)

-Friday 5th, ≈ 14:00h: Stop of the heat run from the CCC

-Friday 5th, just after stopping the heat run, temperatures measurements on the converters (Bernard Dubois)

-Friday 5th , consignation of the converters (Jacky Mazet)

-Friday 5th, after consignations of the converters: the covers will be put in place (Jacky Mazet)

Comments:

Edit, attach file or add comment


Created by Main.MariaPazCasasLino on 2007-10-03 - 15:15

Warm Magnets Commissioning Poin 6. Action list for the 24h heat run and polarity test

Comments:

Edit, attach file or add comment