Created by Main.RosarioPrincipe on 2006-10-06 - 11:48
Enclose the minutes of our last RAT meeting in point 5.
Main subject: 13kA EE switch test.
Also includea a small status of the works in UA63.
Regards

RAT_20061006.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint5x2006x10x06x11x46/RAT_20061006.pdf
Comments:
Edit, attach file or add comment
Created by Main.AntonioVergara on 2006-10-06 - 11:29

DR_RAT_060906.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint0x2006x10x06x11x28/DR_RAT_060906.pdf
Comments:
Edit, attach file or add comment
Created by Main.JacekSzkutnik on 2006-10-06 - 10:12
Please find Infra Red Analysis of RR53 & USC55 during 24H burnin tests at ultimate current of 2006-10-04.
https://edms.cern.ch/file/781901/1/RR53-USC55_IR-Report_2006-10-04_24H-Burnin.pdf
All raw pictures (IR or not) are located in EDMS doc:
https://edms.cern.ch/document/781901/1
IR Tunnel Tests EDMS doc should be located in a dedicated place under EDMS Tunnel installation structure to compare results if needed between locations measured. Note that UA83 is at following address:
https://edms.cern.ch/document/672600/1
.
Jeff Thomsen & Yves Thurel
Comments:
Edit, attach file or add comment
Created by Main.JacekSzkutnik on 2006-10-06 - 09:32
First visit to point 6. The reason of the visit was to know the situation of the power converters, the cables in the tunnel side and in the power converter side. Also, the objetive was to make a first inspection of what we'll find in the short circuit test.

P1000018.JPG:
The air cooled cables was already prepared for the short circuit test

P1000003.JPG:
The water cooled cables still not conected to power converter

P1000004.JPG:
The water cooled cables still not conected to power converter

P1000012.JPG:
The labels of the connection between the power converter and the energy extraction system was made with one single label, the cablotheque id number

P1000020.JPG:
The air cooled cables was already prepared for the short circuit test

P1000016.JPG:
In the tunnel side, the blocks of the water cooled cables were put in all the cables, and placed in the DFB situation

P1000002.JPG:
The water cooled cables still not conected to power converter

P1000017.JPG:
Example of the identification of the water cooled cables.

P1000010.JPG:
The air cooled cables was already connected to the power converters

P1000021.JPG:
The water cooled cables of the DFBMM.4L6 was being hung up in the moment of the visit.