Created by Main.BorisBellesia on 2007-04-18 - 13:19

RAT_20071704.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint3x2007x04x18x13x15/RAT_20071704.pdf
**********************************
**********************************
In the Minutes:
* Resume of the two 8hr heat runs
* List of the contact people of the concerned system during the 24hr heat run
**********************************
**********************************
Schedule:
22.03 |
DONE |
Polarity Check |
30.03 |
DONE |
CCC tests: preparation for the 8hr run |
16.04 |
DONE |
First 8hr HEAT RUN ; re-scheduled |
17.04 |
DONE |
Second 8hr HEAT RUN |
18.04 |
- |
CCC tests: preparation for the 24hr run |
19.04 |
- |
24hr HEAT RUN |
20.04 |
- |
AUG - UPS test |
21.05 |
- |
EE 4hr run |
Edit, attach file or add comment
Created by Main.BorisBellesia on 2007-04-13 - 15:28

RAT_20071204.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint3x2007x04x13x15x22/RAT_20071204.pdf

SOC_settings_8hrun_UJ33.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint3x2007x04x13x15x22/SOC_settings_8hrun_UJ33.pdf
**********************************
**********************************
1 - TS-CV confirmed that the ED circuit of the sector 2-3 will be normally operated the 16th-17th and the 19th.
**********************************
**********************************
2 - In attachment: the current of each PC in UJ33 in the 4 steps of the 8hr run.
* HEAT RUNS Schedule:
22.03 |
DONE |
Polarity Check |
30.03 |
DONE |
CCC tests: preparation for the 8hr run |
16.04 |
- |
First 8hr HEAT RUN ; re-scheduled |
17.04 |
- |
Second 8hr HEAT RUN |
18.04 |
- |
CCC tests: preparation for the 24hr run |
19.04 |
- |
24hr HEAT RUN |
20.04 |
- |
AUG - UPS test |
21.05 |
- |
EE 4hr run |
Edit, attach file or add comment
Created by Main.BorisBellesia on 2007-04-04 - 12:31

RAT_20070404.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint3x2007x04x04x12x30/RAT_20070404.pdf
Comments:
Edit, attach file or add comment
Created by Main.BorisBellesia on 2007-04-02 - 19:02

RAT_20070402.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint3x2007x04x02x18x56/RAT_20070402.pdf
Comments: HEAT RUN CANCELLED
- Maintenance of the water-cooling circuits coming form Point 2 providing water also to the cooling circuits of the power converters in UJ33 was planned to be performed between 02.04 (today) and the 20.04. This manipulation was not taken into account during the planning of the SCT in UJ33.
- The maintenance caused the stop of the tests and was irreversible: it will be not possible recuperate the cooling power until the end of the intervention.
- The tests has been rescheduled in agreement with TS-CV. The priority will be given to the work in SX2 (the primary circuit) in order that the water in UJ33 will be available the 16.04.
HEAT RUNS Schedule:
22.03 |
DONE |
Polarity Check |
30.03 |
DONE |
CCC tests: preparation for the 8hr run |
2.04 |
CANCELLED |
First 8hr HEAT RUN |
16.04 |
- |
First 8hr HEAT RUN ; re-scheduled |
17.04 |
- |
Second 8hr HEAT RUN |
18.04 |
- |
CCC tests: preparation for the 24hr run |
19.04 |
- |
24hr HEAT RUN |
20.04 |
- |
AUG - UPS test |
23.04 |
- |
EE 4hr run |
Edit, attach file or add comment