TWiki home Point 1 Point 2 Point 3 Point 4 Point 5 Point 6 Point 7 Point 8 Minutes

Create new blog entry for Point 5


Created by Main.MirkoPojer on 2006-12-05 - 12:58

Special RAT on SCT in RR57/UJ56 and ECR application, Dec 5

PDF RAT_20061205.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint5x2006x12x05x12x51/RAT_20061205.pdf

PowerPoint RQ4-RQ10-ECR.ppt:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint5x2006x12x05x12x51/RQ4-RQ10-ECR.ppt

Microsoft Excel Spreadsheet RR57-UJ56-8H-24H-PC_LIST.xls:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint5x2006x12x05x12x51/RR57-UJ56-8H-24H-PC_LIST.xls

Comments:

Please find enclosed the list of PC which will be powered during the 8h heat run and the 24h heat run. The list of steps to be implemented following the ERC (EDMS No.804188) is also included

Open Issues

  • 22.11 Fire detection – awaiting certification
  • 01.12 Short cables on 13 kA EE to be changed later on (temporary solution in place)

Edit, attach file or add comment


This topic: HCC > BlogHccDec
Topic revision: r2 - 2006-12-11 - JacekSzkutnik