Created by Main.MirkoPojer on 2006-12-07 - 12:36

RAT_20061207.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint5x2006x12x07x12x32/RAT_20061207.pdf
Comments: Next meeting in CCC on Monday Dec,11.
Open Issues
- 22.11 Fire detection – awaiting certification
- 01.12 Short cables on 13 kA EE to be changed later on (temporary solution in place)
- 06.12 Permanent labels for RQ converters in RR57 (according to ECR)
- 07.12 Cables re-distribution for 600 A
- 07.12 Access key to electrical distribution room in UJ56
Heat Runs and Test Schedule
- 07.12 Fire detection test
- 08.12 Full power ventilation tests in RR57 – from 8:30 till 12:00
- 08.12 Afternoon: Polarity Test_1st part
- 11.12 10am: 24-h heat run
- 12.12 UPS test.
- 13.12 Electric cut (AUG simulation).
- 13.12 Polarity Test_2nd part
- 14.12 13kA energy extraction test.