Created by Main.MatteoSolfaroli on 2007-06-27 - 18:52
Going on activities in sector 45
- DFBAH and MB (diode)
- checked and closed by Wednesday 27th;
- Leak test on Thursday 28th;
- Purging on Friday 29th evening and all the week end long;
- Refilling on Monday 2nd July;
- On Tuesday 3th July, once 6Bar conditions are reached, ElQA will be repeated (only on RB);
- CRYO-instrumentation
- Initialization of RF valves on Wednesday 27th or Thursday 28th;
- Coherence test of all the valves in ARC and LSS (Thursday 28th and Friday 29th);
- Commissioning;
- Initialization of the CV910 valves on Tuesday 26th and Wednesday 27th;
- TS/EL intervention
- Changing of the connectors of a BPM (LSS4R);
- Placing of some Radmon cables on Wednesday 27th, Thursday 28th and Friday 29th (LSS5L);
- Connection check of the instrumentation cables of BCT;
- TIM camera
- General check on Monday 2nd July;
- Run from P4 to P5, during the Cryo Patrouille the morning of the start of the cool-down;
- Safety Inspection
- RAMSES
- Check of the equipment on Tuesday 26th and Wednesday 27th.
- CV Intervention
- Thursday 28th June from 2pm to 4pm
- QUI
- Caps removal, sleeve installation and then closure of the QUI performed on Thursday 28th.
- The new mechanism for the header B valve is being prepared and should be ready for Friday 29th or early next week.