Activities in sector 45 from Monday 2nd July
- CRYO
- Purging on Friday 29th evening and all the week end long;
- Refilling on Monday 2nd July;
- ElQA-TP4B and Monitoring installation
- On Tuesday 3th July, once 6Bar conditions are reached, ElQA will be repeated (only on RB) maybe from 8am to 1pm. RESTRICTED ACCESS.
- CRYO-instrumentation
- Coherence test of all the valves in ARC and LSS (Thursday 28th and Friday 29th);
- Commissioning;
- Initialization of the CV910 valves on Tuesday 26th and Wednesday 27th;
- TS/EL intervention
- Changing of the connectors of a BPM (LSS4R);
- Connection check of the instrumentation cables of BCT;
- TIM camera
- General check on Monday 2nd July;
- Run from P4 to P5, during the Cryo Patrouille the morning of the start of the cool-down;
- Safety Inspection
- AT/ACR Patrouille
- A Patrouille will be carried out on Wednesday 4th July just before the cooldown.
- AT/VAC
- Short access to LSS4R and LSS5L on Monday 2nd July.
- AB/BI
- LSS4R short intervention on the BI (capeau).