Create new blog entry for Point 8


Created by Main.BorisBellesia on 2007-06-13 - 20:48

D2 Quench

Bitmap quench_d2_q4.bmp:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint8x2007x06x13x20x32/quench_d2_q4.bmp

Bitmap D2-Q4.bmp:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint8x2007x06x13x20x32/D2-Q4.bmp

Comments:

Edit, attach file or add comment


Created by Main.BorisBellesia on 2007-06-13 - 15:55

Powering of sector 78 - Report of 13.06.2007

Report of Wednesday 13.06.2007

  • ElQA
    • Tests in MBA during all the day.
  • RQ5.L8:
    • Calibration test performed by AB/PO. Test ongoing.
  • RD2.L8:
    • Ramped to 200A. Quench heater fired. Post-mortem data acquired properly. Test OK
    • Ramped to 1kA. Quench heater fired. Post-mortem data acquired properly. Test OK
  • RQF and RQD
    • Quench heater charge.
  • RD2.L8
    • Test 1 on the ML8 performed. D2 quenched when R4.L8B1 was at 2.2kA and R4.L8B2 was around 3kA ramping to 3.61kA. Test NOT OK.

Planning for Thursday 14.06.2007

AM:

  • ElQA on MB with instrumentation + QF & QD
  • RQ6.R7B1 and RQ6.R7B2: Repeat test
  • QPS IST RQF.A78 and RQD.A78: discharge of the heaters
  • RD2.L8 to nominal
  • RQ5.L8 and their correctors calibration by PO (UA)
PM:
  • 600 A circuits of L8: PCC (<20A) for all
  • 600 A circuits of L8: PIC2 for all
  • 600 A circuits of L8:PCS.1 for all
  • List of the 600A circuits released by AT/MEL and AT/ACR
    • RQTL12.L8B1
    • RQTF.A78B1
    • RQTF.A78B2
    • RSD1.A78B2
    • RQS.L8B1
    • RSD2.A78B1
    • RSF1.A78B1
    • RSF1.A78B2
    • RCO.A78B1
  • AB/PO Type tests on 60A converter

Edit, attach file or add comment

Edit | Attach | Watch | Print version | History: r1 | Backlinks | Raw View | WYSIWYG | More topic actions
Topic revision: r1 - 2007-06-01 - JacekSzkutnik
 
    • Cern Search Icon Cern Search
    • TWiki Search Icon TWiki Search
    • Google Search Icon Google Search

    HCC All webs login