Powering Tests Sector 7-8 - 19.07.2007

Test Report from Tuesday 19.07.2007

  • RQD.A78:
    • Transfer function measurements with 60A converter completed OK
    • PCC Circuit Config tests completed
    • PIC2 - All steps completed OK except:
      • Circuit discharge from power converter: switches were not rearmed after PM data generation - Test to be repeated
      • Discharge request from PIC - to be done

  • RQF.A78:
    • Transfer function measurements with 60A converter completed OK
    • PCC Circuit Config tests completed
    • PIC2 - All steps completed OK up to Powering Failure test (included)

  • RQ4.L8 and RD2.L8:
    • Tests 1 and 2 proposed by MPP completed but without provoking an artificial quench at the end of the second. Detection threshold still at 20mV. Still no quench. Further research to be done.

  • RCO.A78B1 powered below 20A for QPS analysis. The circuit is still blocked till the new sofware is uploaded.

Test Plan for Wednesday 20.07.2007

  • Resolution of cable signal/interlock swap F/D

  • RQD.A78 (from the CCC):
    • Last two steps of PIC2
    • PLI1 (750A)
    • PLI2 (2000A)
    • PLI3 (6500A)

  • RQF.A78 (from the CCC):
    • Complete PIC2
    • First steps of PLI1,2,3 if possible

  • RB.A78
    • IST Energy extraction tests, PIC1, connection of the leads

  • Matching section:
    • Type analysis of the power converters
    • Analyse boil-off data and eventually repeat a more complete boil-off
    • Waiting for new proposals from MPP
    • 120A converter on Q5 type tests

Edit, attach file or add comment


Created by Main.AntonioVergara on 2007-06-19 - 15:21

Powering RQD.A78 and RQF.A78

  • PIC2 - I = I_MIN_OP = 350A

  • PLI1 - I = I_INJECTION = 760A
    • PLI1.1 - Current cycle: 350A to 760A at 10 A/s
    • PLI1.2 - Energy extraction discharge at 760A (bus-bar or current lead quench)
    • PLI1.3 - Powering failure from power converter
    • PLI1.4 - FPA from PIC
    • PLI1.5 - Quench heater firing
      • SSS049 15L8

  • PLI2 - I = I_INTERM_1 = 2000A
    • PLI2.1 - Current cycle: 350A to 2000A at 10 A/s
    • PLI2.2 - Energy extraction discharge at 2000A (bus-bar or current lead quench)
    • PLI2.3 - Slow Power Abort from PIC
    • PLI2.4 - Quench heater firing
      • SSS016 24R7

  • PLI3 - I = I_INTERM_2 = 6500A
    • PLI3.1a - Currrent cycle: 350A to 6500A at 10 A/s
    • PLI3.2 - Energy extraction discharge at 6500A (bus-bar or current lead quench)
    • PLI3.3 - Quench heater firing

Edit, attach file or add comment

Edit | Attach | Watch | Print version | History: r1 | Backlinks | Raw View | WYSIWYG | More topic actions