Created by Main.AntonioVergara on 2007-06-20 - 20:20
Test Report of Wednesday 20.6.2007
- RQF.A78
- PIC2 completed up to Fast Power Abort from PIC - Test OK
- RQD.A78
- PIC2 tests completed - OK
- PLI1 tests at 760A completed - OK
- PLI2 tests at 2000A completed - OK
- PLI3 started. RQD.A78 circuit ramped up successfully to 6400A, kept there for more than one hour. - OK
- Champagne and pictures
- PLI3.1 test completed - Magnet ramped up to 6500A and down to 350A successfully!!
- Matching section
- Type tests on different circuits performed by AB/PO
Planning for Thursday 21.06.2007
- RQD.A78
- PLI3.2 Discharge request
- PLI3.3 Quench heater discharge
- RB.A78
- After tests completed in RQD.A78 (in parallel):
- QPS IST tests
- Connection of the current leads in DFBAO and DFBAN
- PIC1
- Connection of the 60A converter - Transfer function measurement
- Cabling repair 600A - RCS, RCD circuits.
- Wait for DFBAN release from ACR
- 600 Circuits - Further measurements by QPS - Depending on Reiner's progress in RB, which has full pripority.
- Matching section
- Type tests AB/PO continue
- ACR checks on the DFBMA current leads with D2 at nominal current
Edit, attach file or add comment