Created by Main.AntonioVergara on 2007-06-21 - 20:12
Test Report of Thursday 21.06.2007
- RQD.A78
- PLI3.2 Discharge Request - Test OK
- PLI3.3 Quench heater discharge in 12R7 - Test OK - Cryo_Maintain was recovered after 10 minutes and Cryo_Start in about 30 minutes.
- RQF.A78
- PIC2 completed - Test OK
- PLI1.1 - Current cycle at 760A completed - Test OK
- PLI1.3 - PC Failure at 760A completed - Test OK
- Communication problems with the energy extraction controller prevented from closing the switches remotely. Tests stopped.
- RB.A78
- QPS IST completed - 2 DQHDS had to be replaced
- A communication problem came up due to a corrupted code line maybe caused during the downloading of the last software version.
- Current leads connected to DC cables in DFBAO and DFBAN
- Last corrections being done by QPS experts
- Matching Section
- Heat runs continue during the whole week with RD2 and RQ5
- Type tests of the converters by AB/PO completed.
Planning for Friday 22.06.2007
- RB.A78
- PIC1
- Connection of the 60A conveter and TF measurement
- Connection of the RB converter to the circuit+ PCC
- PIC2
- RQF.A78 (in parallel with RB whenever possible)
- Complete PLI1 (760A)
- Energy extraction discharge
- FPA
- Discharge request from PC
- Heater firing
- PLI2 (2000A)
- PLI3 (6500A)
- 60 Closed Orbit Correctors
- PCC and P2N on selected circuits
- AB/PO current stability measurements in RD2.L8
- Empty of DFBMA and Q4/D2 cryostats over the weekend