Created by Main.AntonioVergara on 2007-06-24 - 14:47
Test Report of Friday 22.06.2007
- RB.A78
- PIC1 - Completed OK after a the solution of an adjustment problem in the current loop controller of the QPS (few mA too low).
- Connection of the 60A conveter to the RB circuit in the UA83 side. The TF measurements could not be completed because the converter noise made the bus-bar quench detector trip everytime it was switched on. The detection threshold will be increased on Monday.
- The time out preventing from closing the switches too early after a switch opening has been lowered in order to speed the tests up.
- RQF.A78
- PLI1 (760A) completed - Test OK
- PLI2 (2000A) completed - Test OK
- PLI3.1 (current cycle up to 6500A) completed - Test OK
- 60 Closed Orbit Correctors
- PCC carried out in one circuit.
- All the circuits released by ElQA have been connected to the power converter.
- AB/PO current stability measurements in RD2.L8 - Completed
- Empty of DFBMA and Q4/D2 started in the evening
Test Plan for Monday 25.06.2007
- RB.A78
- Provisional correction of the detection threshold of the bus-bar quench detector in order to allow TF measurement with the 60A converter.
- TF measurement
- Desconnection of the 60A converter and final connection of the RB converter to the circuit; PCC tests
- Set detection threshold back to operation value
- PIC2
- PLI1 (760A)
- PLI1.1 - Current cycle
- PLI1.2 - Energy extraction discharge (quench to a current lead)
- PLI1.3 - Powering Failure from PC
- PLI1.4 - FPA from PIC
- PLI1.5 - Quench heater discharge on a selected magnet
- PLI2 (2000A)
- PLI2.1 - Current cycle
- PLI2.2 - Energy extraction discharge (quench to a current lead)
- PLI2.2b - SPA from PIC
- PLI2.3 - Quench heater discharge on a selected magnet
- RQF.A78 (6500A)
- PLI3.2 - Energy extraction discharge
- PLI3.3 - Quench heater discharge on 12L8 SSS
- 600A Correctors
- Software upgrade by QPS
- PCS tests on the circuits: RQT12.L8B1, RQS.L8B1, RCO.A78B1
- DFBMA will me refilled in the afternoon
- 60A Closed Orbit Correctors: PCC and P2N whenever possible