Powering Tests Sector 7-8 - Report Monday 25.06.2007

Test Report of Monday 25.06.2007

  • RB.A78
    • Provisional correction of the detection threshold of the bus-bar quench detector.
    • TF measurement - Test OK after some corrections done in one QPS crate
    • RB converter connected to the circuit
    • Circuit ramped up to 350A with the bus-bar quench detection threshold increased. Loop properly closed!
    • Some modifications needed in the QPS bus-bar quench detector - Circuit ramped up again to 350A with QPS in operational conditions!!
    • PCC Circuit Config - TEST OK!

  • RQF.A78 (6500A)
    • PLI3.2 - Energy extraction discharge - Test OK
    • PLI3.3 - Quench heater discharge on 12L8 SSS - Test OK

  • 600A Correctors
    • PCS tests on the circuits: RQT12.L8B1, RQS.L8B1, RCO.A78B1 - Going on

  • DFBMA refilled and cooled down in a couple of hours

  • 60A Closed Orbit Correctors: PCC in 16 converters

Test Plan for Tuesday 26.06.2007

  • RB.A78
    • PIC2
    • PLI1 (760A)
      • PLI1.1 - Current cycle
      • PLI1.2 - Energy extraction discharge (quench to a current lead)
      • PLI1.3 - Powering Failure from PC
      • PLI1.4 - FPA from PIC
      • PLI1.5 - Quench heater discharge on LBBRG.10L8 (magnet 1030)
    • PLI2 (2000A)
      • PLI2.1 - Current cycle
      • PLI2.2 - Energy extraction discharge (quench to a current lead)
      • PLI2.2b - SPA from PIC
      • PLI2.3 - Quench heater discharge on LBBRA.13L8 (magnet 3002) and LBARA.13R7 (magnet 1054)

  • Matching Section: Powered to the same conditions of the triple quench on 31/06 once the quench detection threshold has been increased to operational values.

  • 60A closed orbit correctors: PCC and P2N

  • RQF.A78 or RQD.A78
    • Type tests
    • Quench campaign:
      • RQF and RQD ramped up together to 6500A. Quench TWO quadrupoles in different cryogenic cells simmultaneously.
      • RQF and RQD ramped up together to 6500A. Quench FOUR quadrupoles in different cryogenic cells simmultaneously.

  • 600A correctors
    • Study and debugging of the quench detectors going on.

Edit, attach file or add comment

Edit | Attach | Watch | Print version | History: r1 | Backlinks | Raw View | WYSIWYG | More topic actions
Topic revision: r1 - 2007-06-01 - JacekSzkutnik
 
    • Cern Search Icon Cern Search
    • TWiki Search Icon TWiki Search
    • Google Search Icon Google Search

    HCC All webs login