Powering Tests Sector 7-8 - Tuesday 26.06.2007

PDF Progress_PoweringS78_070627.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint8x2007x06x26x19x45/Progress_PoweringS78_070627.pdf

Test Report from Tuesday 26.06.2007

  • RB.A78
    • PIC2 - Test completed OK
    • During the whole day, the noise read by the bus-bar quench detector of the circuit tripped several times. The source of the noise (period of about 20 minutes) has not been identified yet.
    • PLI1 (760A)
      • PLI1.1 - Current cycle - Test OK
      • PLI1.2 - Energy extraction discharge (quench to a current lead) - Test OK
      • PLI1.3 - Powering Failure from PC - Test OK

  • RQ5.L8: Commissioned up to PLI3 using the sequencer - Tests OK

  • 60A closed orbit correctors - P2N completed for one corrector using new automated procedure

  • RQF.A78 - Type test completed - Test OK

  • 600A correctors
    • RCO.A78 and RQT12.L8B1 - PCS completed - Test OK

Test Plan for Wednesday 27.06.2007

  • Show goes from 7:00 to 22:00

  • RB.A78
    • PLI1.4 - FPA from PIC
    • PLI1.5 - Quench heater discharge on A28.R7
    • PLI2 (2000A)
      • PLI2.1 - Current cycle
      • PLI2.2 - Energy extraction discharge (quench to a current lead)
      • PLI2.2b - SPA from PIC
      • PLI2.3 - Quench heater discharge on LBBRA.13L8 (magnet 3002) and LBARA.13R7 (magnet 1054)

  • RQF.A78 and RQD.A78 (once RB.A78 tests are completed)
      • RQF and RQD ramped up together to 6500A. Quench on 15L8
      • RQF and RQD ramped up together to 6500A. Quadruple quench 20L8, 19L8, 19R7 and 22R7 .

  • Simmultaneous powering of RQF.A78, RQD.A78 and RB.A78.

  • 600A Correctors - More circuits will be released in the afternoon by QPS for PCS tests

  • 60A Closed Orbit Correctors
    • P2N will continue
    • Type tests for some converters in the evening after quenches in the main circuits

  • Matching Section
    • Reproduction of the quench event of May 31st
    • Last commissioning step of RQ5.L8 via the sequencer

  • AB/PO (David) will prepare a list of the activities to be carried out in the conveters already commissioned before the warm-up

Edit, attach file or add comment

Edit | Attach | Watch | Print version | History: r1 | Backlinks | Raw View | WYSIWYG | More topic actions
Topic revision: r1 - 2007-06-01 - JacekSzkutnik
 
    • Cern Search Icon Cern Search
    • TWiki Search Icon TWiki Search
    • Google Search Icon Google Search

    HCC All webs login