Created by Main.AntonioVergara on 2007-06-26 - 20:06

Progress_PoweringS78_070627.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint8x2007x06x26x19x45/Progress_PoweringS78_070627.pdf
Test Report from Tuesday 26.06.2007
- RB.A78
- PIC2 - Test completed OK
- During the whole day, the noise read by the bus-bar quench detector of the circuit tripped several times. The source of the noise (period of about 20 minutes) has not been identified yet.
- PLI1 (760A)
- PLI1.1 - Current cycle - Test OK
- PLI1.2 - Energy extraction discharge (quench to a current lead) - Test OK
- PLI1.3 - Powering Failure from PC - Test OK
- RQ5.L8: Commissioned up to PLI3 using the sequencer - Tests OK
- 60A closed orbit correctors - P2N completed for one corrector using new automated procedure
- RQF.A78 - Type test completed - Test OK
- 600A correctors
- RCO.A78 and RQT12.L8B1 - PCS completed - Test OK
Test Plan for Wednesday 27.06.2007
- Show goes from 7:00 to 22:00
- RB.A78
- PLI1.4 - FPA from PIC
- PLI1.5 - Quench heater discharge on A28.R7
- PLI2 (2000A)
- PLI2.1 - Current cycle
- PLI2.2 - Energy extraction discharge (quench to a current lead)
- PLI2.2b - SPA from PIC
- PLI2.3 - Quench heater discharge on LBBRA.13L8 (magnet 3002) and LBARA.13R7 (magnet 1054)
- RQF.A78 and RQD.A78 (once RB.A78 tests are completed)
-
- RQF and RQD ramped up together to 6500A. Quench on 15L8
- RQF and RQD ramped up together to 6500A. Quadruple quench 20L8, 19L8, 19R7 and 22R7 .
- Simmultaneous powering of RQF.A78, RQD.A78 and RB.A78.
- 600A Correctors - More circuits will be released in the afternoon by QPS for PCS tests
- 60A Closed Orbit Correctors
- P2N will continue
- Type tests for some converters in the evening after quenches in the main circuits
- Matching Section
- Reproduction of the quench event of May 31st
- Last commissioning step of RQ5.L8 via the sequencer
- AB/PO (David) will prepare a list of the activities to be carried out in the conveters already commissioned before the warm-up
Edit, attach file or add comment