Created by Main.JacekSzkutnik on 2007-03-30 - 12:55

SCT in UJ33 - 30th March

PDF RAT_20070330.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint3x2007x03x30x12x53/RAT_20070330.pdf

************ 8hr HAET RUN: Monday 02.04 - Tuesday 03.04 ************

HEAT RUNS Schedule:

22.03 ON GOING Polarity Check
30.03 ON GOING CCC tests: preparation for the 8hr run
2.04 - First 8hr HEAT RUN
3.04 - Second 8hr HEAT RUN
11.04 - CCC tests: preparation for the 24hr run
12.04 - 24hr HEAT RUN
12.04 - AUG - UPS test
13.04 - EE 4hr run

Edit, attach file or add comment


Created by Main.BorisBellesia on 2007-03-26 - 19:51

SCT in UJ33 - 26th March

PDF RAT_20070326.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint3x2007x03x26x19x45/RAT_20070326.pdf

HEAT RUNS

22.03 - Polarity Check
30.03 - CCC tests: preparation for the 8hr run
2.04 - First 8hr HEAT RUN
3.04 - Second 8hr HEAT RUN
11.04 - CCC tests: preparation for the 24hr run
10.04 - 24hr HEAT RUN
12.04 - AUG - UPS test
13.04 - EE 4hr run

Edit, attach file or add comment


Created by Main.BorisBellesia on 2007-03-23 - 17:22

SCT in UJ33 - 23th March

PDF RAT_20070323.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint3x2007x03x23x17x16/RAT_20070323.pdf

PDF Etude-sect-cablesDC-UJ33-tot.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint3x2007x03x23x17x16/Etude-sect-cablesDC-UJ33-tot.pdf

ATTACHED: Machine Profile for the 8hr run in UJ33: Power Converters Utilization Factors

EE sys IST

6.03 DONE 600A EE systems IST - DFBLC
12.03 DONE 600A EE systems IST - DFBAE
16.03 DONE 600A EE systems IST - DFBM
6.03 DONE 13kA EE systems IST - L7
13.03 DONE 13kA EE systems IST - R7
DFBLC
14.03 DONE 600A no EE PC – IST
15.03 DONE 600A-EE interlock tests
15.03 DONE 600A-EE PC - IST
DFBAE+120A UJ33L
20.03 DONE 600A no EE PC; IST
23.03 DONE 600A-EE Interlock tests
23.03 DONE 600A-EE powering
28.03 DONE 120A; powering
DFBMD - L&R
29.03 DONE 120A - DFBM - powering
29.03 DONE 600A-EE interlock tests
29.03 DONE 600A-EE powering
WARM-MAGN. PC+120A UJ33R
2.04 DONE 600A - Warm magnets
4.04 DONE 120A 1; powering
HEAT RUNS
5.04 - 8hr HEAT RUN
6.04 - CCC tests
10.04 - 24hr heat run test
2.04 - Polarity Check
12.04 - EE 4hr run
13.04 - AUG- UPS test

Edit, attach file or add comment


Created by Main.MatteoSolfaroli on 2007-03-21 - 14:25

SCT in UJ33 - 21st March

PDF RAT_20070321.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint3x2007x03x21x14x20/RAT_20070321.pdf

Comments: EE sys IST

6.03 DONE 600A EE systems IST - DFBLC
12.03 DONE 600A EE systems IST - DFBAE
16.03 DONE 600A EE systems IST - DFBM
6.03 DONE 13kA EE systems IST - L7
13.03 DONE 13kA EE systems IST - R7
DFBLC
14.03 DONE 600A no EE PC – IST
15.03 DONE 600A-EE interlock tests
15.03 DONE 600A-EE PC - IST
DFBAE+120A UJ33L
20.03 ON GOING 600A no EE PC – IST
23.03 DONE 600A-EE Interlock tests
23.03 DONE 600A-EE powering
28.03 DONE 120A – powering
DFBMD - L&R
29.03 - 120A - DFBM - powering
29.03 - 600A-EE interlock tests
29.03 - 600A-EE powering
WARM-MAGN. PC+120A UJ33R
2.04 ONGOING 600A - Warm magnets
4.04 - 120A – powering
HEAT RUNS
5.04 - 8hr HEAT RUN
6.04 - CCC tests
10.04 - 24hr heat run test
2.04 - Polarity Check
12.04 - EE 4hr run
13.04 - AUG- UPS test

Edit, attach file or add comment


Created by Main.BorisBellesia on 2007-03-19 - 11:36

SCT in UJ33 - 19th March

PDF RAT_20070319.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint3x2007x03x19x11x30/RAT_20070319.pdf

EE sys IST

6.03 DONE 600A EE systems IST - DFBLC
12.03 DONE 600A EE systems IST - DFBAE
16.03 DONE 600A EE systems IST - DFBM
6.03 DONE 13kA EE systems IST - L7
13.03 DONE 13kA EE systems IST - R7
DFBLC
14.03 DONE 600A no EE PC – IST
15.03 DONE 600A-EE interlock tests
15.03 DONE 600A-EE PC - IST
DFBAE+120A UJ33L
20.03 ON GOING 600A no EE PC – IST
23.03 DONE 600A-EE Interlock tests
23.03 ON GOING 600A-EE powering
28.03 - 120A – powering
DFBMD - L&R
29.03 - 120A - DFBM - powering
29.03 - 600A-EE interlock tests
29.03 - 600A-EE powering
WARM-MAGN. PC+120A UJ33R
2.04 - 600A - Warm magnets
4.04 - 120A – powering
HEAT RUNS
5.04 - 8hr HEAT RUN
6.04 - CCC tests
10.04 - 24hr heat run test
2.04 - Polarity Check
12.04 - EE 4hr run
13.04 - AUG- UPS test

Edit, attach file or add comment


Created by Main.BorisBellesia on 2007-03-15 - 19:18

SCT in UJ33 - 15th Mar.

PDF RAT_20070315.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint3x2007x03x15x18x46/RAT_20070315.pdf

EE sys IST

6.03 DONE 600A EE systems IST - DFBLC
12.03 DONE 600A EE systems IST - DFBAE
16.03 DONE 600A EE systems IST - DFBM
6.03 ON GOING 13kA EE systems IST - L7
13.03 DONE 13kA EE systems IST - R7
DFBLC
14.03 ON GOING 600A no EE PC – IST
15.03 ON GOING 600A-EE interlock tests
15.03 ON GOING 600A-EE PC - IST
DFBAE+120A UJ33L
20.03 - 600A no EE PC – IST
23.03 - 600A-EE Interlock tests
23.03 - 600A-EE powering
28.03 - 120A – powering
DFBMD - L&R
29.03 - 120A - DFBM - powering
29.03 - 600A-EE interlock tests
29.03 - 600A-EE powering
WARM-MAGN. PC+120A UJ33R
2.04 - 600A - Warm magnets
4.04 - 120A – powering
HEAT RUNS
5.04 - 8hr HEAT RUN
6.04 - CCC tests
10.04 - 24hr heat run test
2.04 - Polarity Check
12.04 - EE 4hr run
13.04 - AUG- UPS test

Edit, attach file or add comment


Created by Main.BorisBellesia on 2007-03-13 - 20:25

SCT in UJ33 - 13th Mar.

PDF RAT_20070313.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint3x2007x03x13x20x24/RAT_20070313.pdf

Comments:

Edit, attach file or add comment


Created by Main.BorisBellesia on 2007-03-08 - 11:47

SCT in UJ33 - 8th Mar.

PDF RAT_20070308.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint3x2007x03x08x11x39/RAT_20070308.pdf

PDF Rapport_de_visite_du_7_mars_2007_point_3.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint3x2007x03x08x11x39/Rapport_de_visite_du_7_mars_2007_point_3.pdf

Comments:

Edit, attach file or add comment


Created by Main.BorisBellesia on 2007-03-06 - 17:21

SCT in UJ33 - 6th Mar.

PDF UJ33.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint3x2007x03x06x17x18/UJ33.pdf

Attached file contains:

  • Short Circuit Test Schedule

  • UJ33 Area divided with respect to the concerned circuits

  • Circuits names

Edit, attach file or add comment