TWiki home Point 1 Point 2 Point 3 Point 4 Point 5 Point 6 Point 7 Point 8 Minutes

Create new blog entry for Point 2


Created by Main.BorisBellesia on 2007-05-22 - 19:44

Short Circuit Tests - 21st May

PDF RAT_20070521.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint2x2007x05x22x19x40/RAT_20070521.pdf

PDF sct_UA27_v005.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint2x2007x05x22x19x40/sct_UA27_v005.pdf

  • SCT planning attached

EE - IST    
13kA EE DONE 16-04-07
600A EE DONE 23-04-07
     
Circuits >2kA    
Powering tests PC 4-8kA - 11-05-07
8h run 4-8kA ON GOING 29-05-07
Interlock tests RQD&F - 02-05-07
Powering tests RQD&F - 24-05-07
Preparation RB.A23 ON GOING 19-04-07
Interlock tests RB.A23 - 29-05-07
Powering tests RB.A23 - 30-05-07
8h run >= 8kA - 04-06-07
     
Circuits < 2kA    
120A powering tests DONE 03-05-07
600ANOEE powering tests ON GOING 08-05-07
600A-EE interlock tests ON GOING 03-05-07
600A-EE powering tests DONE 18-05-07
8 hr run PC < 2kA - 29-05-07
     
24hr heat run test - 07-06-07
     
Polarity Check < 8KA - 30-05-07
AUG- UPS test - 08-06-07

Edit, attach file or add comment


This topic: HCC > BlogHccMay07
Topic revision: r1 - 2007-05-02 - JacekSzkutnik