Short Circuit Test UA27 - 29th May

PDF RAT_20070529.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint2x2007x05x29x11x06/RAT_20070529.pdf

**********************************

8hr heat run ON GONIG: all circuits belonging to the powering sub-sector MR2 and A23 (but 13kA)

**********************************

EE - IST    
13kA EE DONE 16-04-07
600A EE DONE 23-04-07
     
Circuits >2kA    
Powering tests PC 4-8kA DONE 11-05-07
8h run 4-8kA ONGOING 29-05-07
Interlock tests RQD&F ONGOING 30-05-07
Powering tests RQD&F - 30-05-07
Preparation RB.A23 DONE 19-04-07
Interlock tests RB.A23 DONE 25-05-07
Powering tests RB.A23 - 30-05-07
8h run >= 8kA - 04-06-07
     
Circuits < 2kA    
120A powering tests DONE 03-05-07
600ANOEE powering tests DONE 08-05-07
600A-EE interlock tests DONE 03-05-07
600A-EE powering tests DONE 18-05-07
8 hr run PC < 2kA ONGOING 29-05-07
     
24hr heat run test - 07-06-07
     
Polarity Check < 8KA - 30-05-07
AUG- UPS test - 08-06-07