Created by Main.BorisBellesia on 2007-05-31 - 17:52

Short Circuit Test in UA27 - 31st May

Microsoft Excel Spreadsheet SOC_II_8hr_heatrun_UA27.xls:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint2x2007x05x31x17x49/SOC_II_8hr_heatrun_UA27.xls

PDF RAT_20070531.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint2x2007x05x31x17x49/RAT_20070531.pdf

Comments:

EE - IST    
13kA EE DONE 16-04-07
600A EE DONE 23-04-07
     
Circuits >2kA    
Powering tests PC 4-8kA DONE 11-05-07
8h run 4-8kA ONGOING 29-05-07
Interlock tests RQD&F ONGOING 30-05-07
Powering tests RQD&F ONGOING 30-05-07
Preparation RB.A23 DONE 19-04-07
Interlock tests RB.A23 DONE 25-05-07
Powering tests RB.A23 ONGOING 30-05-07
8h run >= 8kA - 04-06-07
     
Circuits < 2kA    
120A powering tests DONE 03-05-07
600ANOEE powering tests DONE 08-05-07
600A-EE interlock tests DONE 03-05-07
600A-EE powering tests DONE 18-05-07
8 hr run PC < 2kA DONE 29-05-07
     
24hr heat run test - 07-06-07
     
Polarity Check < 8KA - 30-05-07
AUG- UPS test - 08-06-07

Edit, attach file or add comment


Created by Main.BorisBellesia on 2007-05-29 - 11:12

Short Circuit Test UA27 - 29th May

PDF RAT_20070529.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint2x2007x05x29x11x06/RAT_20070529.pdf

**********************************

8hr heat run ON GONIG: all circuits belonging to the powering sub-sector MR2 and A23 (but 13kA)

**********************************

EE - IST    
13kA EE DONE 16-04-07
600A EE DONE 23-04-07
     
Circuits >2kA    
Powering tests PC 4-8kA DONE 11-05-07
8h run 4-8kA ONGOING 29-05-07
Interlock tests RQD&F ONGOING 30-05-07
Powering tests RQD&F - 30-05-07
Preparation RB.A23 DONE 19-04-07
Interlock tests RB.A23 DONE 25-05-07
Powering tests RB.A23 - 30-05-07
8h run >= 8kA - 04-06-07
     
Circuits < 2kA    
120A powering tests DONE 03-05-07
600ANOEE powering tests DONE 08-05-07
600A-EE interlock tests DONE 03-05-07
600A-EE powering tests DONE 18-05-07
8 hr run PC < 2kA ONGOING 29-05-07
     
24hr heat run test - 07-06-07
     
Polarity Check < 8KA - 30-05-07
AUG- UPS test - 08-06-07

Edit, attach file or add comment


Created by Main.BorisBellesia on 2007-05-25 - 11:33

Short Circuit Tests in UA27 - 25th May

PDF RAT_20070525.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint2x2007x05x25x11x30/RAT_20070525.pdf

EE - IST    
13kA EE DONE 16-04-07
600A EE DONE 23-04-07
     
Circuits >2kA    
Powering tests PC 4-8kA DONE 11-05-07
8h run 4-8kA - 29-05-07
Interlock tests RQD&F ONGOING 02-05-07
Powering tests RQD&F - 24-05-07
Preparation RB.A23 ON GOING 19-04-07
Interlock tests RB.A23 DONE 25-05-07
Powering tests RB.A23 - 30-05-07
8h run >= 8kA - 04-06-07
     
Circuits < 2kA    
120A powering tests DONE 03-05-07
600ANOEE powering tests DONE 08-05-07
600A-EE interlock tests DONE 03-05-07
600A-EE powering tests DONE 18-05-07
8 hr run PC < 2kA - 29-05-07
     
24hr heat run test - 07-06-07
     
Polarity Check < 8KA - 30-05-07
AUG- UPS test - 08-06-07

Edit, attach file or add comment


Created by Main.BorisBellesia on 2007-05-23 - 12:26

Short Circuit Tests in UA27 - 23rd May

PDF RAT_20070523.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint2x2007x05x23x12x21/RAT_20070523.pdf

Microsoft Excel Spreadsheet SOC_UA27_8hrheatrun.xls:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint2x2007x05x23x12x21/SOC_UA27_8hrheatrun.xls

  • The Set Of Circuits for the 8hr heat run attached. It includes all the circuits ion UA27 but the 13kA and the ones belonging to the powering subsector XR2

EE - IST    
13kA EE DONE 16-04-07
600A EE DONE 23-04-07
     
Circuits >2kA    
Powering tests PC 4-8kA - 11-05-07
8h run 4-8kA ON GOING 29-05-07
Interlock tests RQD&F ONGOING 02-05-07
Powering tests RQD&F - 24-05-07
Preparation RB.A23 ON GOING 19-04-07
Interlock tests RB.A23 - 29-05-07
Powering tests RB.A23 - 30-05-07
8h run >= 8kA - 04-06-07
     
Circuits < 2kA    
120A powering tests DONE 03-05-07
600ANOEE powering tests ON GOING 08-05-07
600A-EE interlock tests ON GOING 03-05-07
600A-EE powering tests DONE 18-05-07
8 hr run PC < 2kA - 29-05-07
     
24hr heat run test - 07-06-07
     
Polarity Check < 8KA - 30-05-07
AUG- UPS test - 08-06-07

Edit, attach file or add comment


Created by Main.BorisBellesia on 2007-05-22 - 19:44

Short Circuit Tests - 21st May

PDF RAT_20070521.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint2x2007x05x22x19x40/RAT_20070521.pdf

PDF sct_UA27_v005.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint2x2007x05x22x19x40/sct_UA27_v005.pdf

  • SCT planning attached

EE - IST    
13kA EE DONE 16-04-07
600A EE DONE 23-04-07
     
Circuits >2kA    
Powering tests PC 4-8kA - 11-05-07
8h run 4-8kA ON GOING 29-05-07
Interlock tests RQD&F - 02-05-07
Powering tests RQD&F - 24-05-07
Preparation RB.A23 ON GOING 19-04-07
Interlock tests RB.A23 - 29-05-07
Powering tests RB.A23 - 30-05-07
8h run >= 8kA - 04-06-07
     
Circuits < 2kA    
120A powering tests DONE 03-05-07
600ANOEE powering tests ON GOING 08-05-07
600A-EE interlock tests ON GOING 03-05-07
600A-EE powering tests DONE 18-05-07
8 hr run PC < 2kA - 29-05-07
     
24hr heat run test - 07-06-07
     
Polarity Check < 8KA - 30-05-07
AUG- UPS test - 08-06-07

Edit, attach file or add comment


Created by Main.MariaPazCasasLino on 2007-05-16 - 17:38

Short Circuit Test UA27 - 16th May

PDF RAT_20070516.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint2x2007x05x16x16x53/RAT_20070516.pdf

PDF sct_UA27_v004.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint2x2007x05x16x16x53/sct_UA27_v004.pdf

Comments: Note that next 18th May, the intervention of the geometers in the UA27 will go on along the day and a WiFi intervention will take place in the morning. During this intervention a lost of the signal is foreseen during about 15 minutes.

     
13kA EE DONE 16-04-07
600A EE DONE 23-04-07
     
Circuits >2kA    
Powering tests PC 4-8kA ON GOING 09-05-07
8h run 4-8kA - 24-05-07
Interlock tests RQD&F - 22-05-07
Powering tests RQD&F - 23-05-07
Preparation RB.A23 ON GOING 19-04-07
Interlock tests RB.A23 - 29-05-07
Powering tests RB.A23 - 30-05-07
8h run >= 8kA - 04-06-07
Pic interface test - 16-06-07
Circuits < 2kA    
120A powering tests DONE 03-05-07
600ANOEE powering tests ON GOING 08-05-07
600A-EE interlock tests - 22-05-07
600A-EE powering tests DONE 08-05-07
8 hr run PC < 2kA - 24-05-07
     
24hr heat run test - 07-06-07
Polarity test < 8KA - 25-05-07
Polarity Check > 8KA - 05-06-07
AUG- UPS test - 08-06-07

Edit, attach file or add comment


Created by Main.MariaPazCasasLino on 2007-05-15 - 14:28

Short Circuit Test UA27 - 14th May

PDF sct_UA27_v003.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint2x2007x05x15x14x19/sct_UA27_v003.pdf

PDF RAT_20070514.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint2x2007x05x15x14x19/RAT_20070514.pdf

Comments: Note that next 16th May, there will not be powering tests and the PIC interface tests will take place as well as an intervention of the geometers in the UA27 along the day.

Note as well that next 18th a WiFi intervention will take place in the morning. During this intervention a lost of the signal is foreseen during about 15 minutes.

     
13kA EE DONE 16-04-07
600A EE DONE 23-04-07
     
Circuits >2kA    
Powering tests PC 4-8kA ON GOING 09-05-07
8h run 4-8kA - 24-05-07
Interlock tests RQD&F - 16-05-07
Powering tests RQD&F - 23-05-07
Preparation RB.A23 ON GOING 19-04-07
Interlock tests RB.A23 - 29-05-07
Powering tests RB.A23 - 30-05-07
8h run >= 8kA - 04-06-07
Pic interface test - 16-06-07
Circuits < 2kA    
120A powering tests DONE 03-05-07
600ANOEE powering tests ON GOING 08-05-07
600A-EE interlock tests - 16-05-07
600A-EE powering tests DONE 08-05-07
8 hr run PC < 2kA - 24-05-07
     
24hr heat run test - 07-06-07
Polarity test < 8KA - 25-05-07
Polarity Check > 8KA - 05-06-07
AUG- UPS test - 08-06-07

Edit, attach file or add comment


Created by Main.BorisBellesia on 2007-05-09 - 10:48

Short circuit test UA27 - 9th May

PDF RAT_20070509.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint2x2007x05x09x10x31/RAT_20070509.pdf

Energy Extraction 600A; Individual Tests are completed. 3 minor problems found (on 16 systems and not 48 as mentionned). Interlock and powering tests completed. Currently installation of temperature- and voltage-probes is on-going. Expected to be completed on May 9. Gert Coelingh

-- Main.BorisBellesia - 09 May 2007

Edit, attach file or add comment


Created by Main.BorisBellesia on 2007-05-07 - 18:54

Short Circuit Test UA27 - 7th May

PDF RAT_20070507.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint2x2007x05x07x18x51/RAT_20070507.pdf

EE - IST    
13kA EE DONE 16-04-07
600A EE DONE 23-04-07
     
Circuits >2kA    
Powering tests PC 4-8kA - 11-05-07
8h run 4-8kA - 29-05-07
Interlock tests RQD&F - 02-05-07
Powering tests RQD&F - 24-05-07
Preparation RB.A23 ON GOING 19-04-07
Interlock tests RB.A23 - 29-05-07
Powering tests RB.A23 - 30-05-07
8h run >= 8kA - 04-06-07
     
Circuits < 2kA    
120A powering tests DONE 03-05-07
600ANOEE powering tests ON GOING 08-05-07
600A-EE interlock tests ON GOING 03-05-07
600A-EE powering tests ON GOING 18-05-07
8 hr run PC < 2kA - 29-05-07
     
24hr heat run test - 07-06-07
     
Polarity Check < 8KA - 30-05-07
AUG- UPS test - 08-06-07

Edit, attach file or add comment


Created by Main.BorisBellesia on 2007-05-04 - 19:27

Short Circuit Test in UA27- Schedule:

EE - IST    
13kA EE DONE 16-04-07
600A EE DONE 23-04-07
     
Circuits >2kA    
Powering tests PC 4-8kA - 11-05-07
8h run 4-8kA - 29-05-07
Interlock tests RQD&F - 02-05-07
Powering tests RQD&F - 24-05-07
Preparation RB.A23 ON GOING 19-04-07
Interlock tests RB.A23 - 29-05-07
Powering tests RB.A23 - 30-05-07
8h run >= 8kA - 04-06-07
     
Circuits < 2kA    
120A powering tests ON GOING 03-05-07
600ANOEE powering tests - 08-05-07
600A-EE interlock tests ON GOING 03-05-07
600A-EE powering tests - 18-05-07
8 hr run PC < 2kA - 29-05-07
     
24hr heat run test - 07-06-07
     
Polarity Check < 8KA - 30-05-07
AUG- UPS test - 08-06-07

Edit, attach file or add comment


Created by Main.MariaPazCasasLino on 2007-05-03 - 13:41

Short Circuit Test in UA27-02May

PDF RAT_20070502.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint2x2007x05x03x13x36/RAT_20070502.pdf

PDF sct_UA27_v002.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint2x2007x05x03x13x36/sct_UA27_v002.pdf

Comments:

Edit, attach file or add comment

Edit | Attach | Watch | Print version | History: r1 | Backlinks | Raw View | WYSIWYG | More topic actions
Topic revision: r1 - 2007-05-02 - JacekSzkutnik
 
    • Cern Search Icon Cern Search
    • TWiki Search Icon TWiki Search
    • Google Search Icon Google Search

    HCC All webs login