Created by Main.BorisBellesia on 2007-05-04 - 19:27
EE - IST |
|
|
13kA EE |
DONE |
16-04-07 |
600A EE |
DONE |
23-04-07 |
|
|
|
Circuits >2kA |
|
|
Powering tests PC 4-8kA |
- |
11-05-07 |
8h run 4-8kA |
- |
29-05-07 |
Interlock tests RQD&F |
- |
02-05-07 |
Powering tests RQD&F |
- |
24-05-07 |
Preparation RB.A23 |
ON GOING |
19-04-07 |
Interlock tests RB.A23 |
- |
29-05-07 |
Powering tests RB.A23 |
- |
30-05-07 |
8h run >= 8kA |
- |
04-06-07 |
|
|
|
Circuits < 2kA |
|
|
120A powering tests |
ON GOING |
03-05-07 |
600ANOEE powering tests |
- |
08-05-07 |
600A-EE interlock tests |
ON GOING |
03-05-07 |
600A-EE powering tests |
- |
18-05-07 |
8 hr run PC < 2kA |
- |
29-05-07 |
|
|
|
24hr heat run test |
- |
07-06-07 |
|
|
|
Polarity Check < 8KA |
- |
30-05-07 |
AUG- UPS test |
- |
08-06-07 |