SCT in UJ33

PowerPoint GlobalAnalysis24hHR_UJ33.ppt:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint3x2007x05x04x18x27/GlobalAnalysis24hHR_UJ33.ppt

  • During the 24hr heat run major problems were found (for a more detailed description see the attached file):
1 - Over-heating of the systems in UJ33 (central part) – TS-EL will re-routing the cables inside the UJ33.

2 - Over- heating of the cables in the tunnel side RZ33 – a vertical cable tray will be positioned parallel to the TS-CV cooling water supports. The tray will host one of the three cable layers that are now placed on the same tray.

  • The re-routing cable works will last approximately up to the third week of June. The integration/cost studies are on going and the possible co-activities interfering with the preparation for the cooldown of the A34 are being taken into account.
A meeting to up-date the "status of the art" is foreseen for Monday 14th. Details will be given.

  • During the inspection of the UJ33 P. Proudlock commented:

1 - ODH system must be foreseen in UJ33 - the DFBLC inside the UJ makes it indispensable

2 - Rectangular ducts (for the geometers) must be closed during the heat-run

Edit, attach file or add comment

Edit | Attach | Watch | Print version | History: r1 | Backlinks | Raw View | WYSIWYG | More topic actions
Topic revision: r1 - 2007-05-02 - JacekSzkutnik
 
    • Cern Search Icon Cern Search
    • TWiki Search Icon TWiki Search
    • Google Search Icon Google Search

    HCC All webs login