Powering Tests - Sector 78 -

Done on Wednesday 16.05.2007

9:30 PIC2 on corrector circuits on DFBMA/C
10:30 PIC2 on corrector circuits on DFBMA/C completed
11:00 Problems on RQ4.L8 solved.
12:00 PCC on RQ4.L8 completed
14:30 Problems on RQ5.L8 solved.
15:20 PCC on RQ5.L8 completed
15:30 PIC2 on D2-Q4-Q5.L8
18:00 PIC2 on RD2-RQ4-RQ5.L8 completed.
18:00 Last test of PIC2 not passed “PIC2.10 Test hardware links”
18:15 Tests end

Schedule for Friday 18.05.2007 in sector 7-8

WHEN CONDITIONS FOR THE ElQA IN THE DFBAs ARE MET:

DFBAO ElQA continuity test
DFBAN ElQA continuity test

WHEN CONDITIONS FOR POWERING ARE MET (CRYO, MPP, MEL) IN THE POWERING SUBSECTOR ML8:

Sub sector ML8 ready for Powering to Nominal
D2-Q4-Q5.L8 Powering to nominal up to PLI2 (<1000A) – Manually
Corrector circuit 120A DFBMC-A Powering to nominal –Via sequencer

WHEN CONDITIONS IN ARC ARE MET GO ON WITH THE PROGRAMME FOR 60A CONVERTERS (ORBIT CORRECTORS) AND 120A (Q7 TO Q10 CORRECTORS) AS WELL AS THE ELQAs IN THE DFBAs X: previous day - X : last day - O : Proposal

  PC_Config PNO.1 PNO.2 PNO.3  
RCBH11_L8B1 X X X X  
RCBV11_L8B2 X X X X  
RCBH12_L8B2 X X X O  
RCBV12_L8B1 X X X O  
RCBH13_L8B1 X X X O  
RCBV13_L8B2 X X X O  
RCBH14_L8B2 X X X O  
RCBV14_L8B1 X X X O  
RCBH15_L8B1 X X O O  
RCBV15_L8B2 X X O O  
RCBH16_L8B2 X X O O  
RCBV16_L8B1 X X O O  
RCBH17_L8B1 -       PC_Config/crowbar tests to be repeated
RCBV17_L8B2 -       PC_Config/crowbar tests to be repeated
RCBH18_L8B2 -       PC_Config/crowbar tests to be repeated
RCBV18_L8B1 -       PC_Config/crowbar tests to be repeated
RCBH23_L8B1 O        
RCBV23_L8B2 O        
RCBH24_L8B2 O        
RCBV24_L8B1 O        
RCBH25_L8B1          
RCBV25_L8B2          
RCBH27_L8B1          
RCBV27_L8B2          
RCBH28_L8B2          
RCBV28_L8B1          
RCBH29_L8B1          
RCBV29_L8B2          
RCBH31_L8B1          
RCBV31_L8B2          
RCBH32_L8B2          
RCBV32_L8B1          

Comments:

Edit, attach file or add comment

Edit | Attach | Watch | Print version | History: r1 | Backlinks | Raw View | WYSIWYG | More topic actions
Topic revision: r1 - 2007-05-02 - JacekSzkutnik
 
    • Cern Search Icon Cern Search
    • TWiki Search Icon TWiki Search
    • Google Search Icon Google Search

    HCC All webs login