Create new blog entry for Point 6


Created by Main.MirkoPojer on 2007-10-31 - 20:49

Installation and Commissioning of the Beam Dump System _ Minutes of 30/10/07 meeting

PDF RAT__20071030.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint6x2007x10x31x20x48/RAT__20071030.pdf

Comments:

Edit, attach file or add comment


Created by Main.MirkoPojer on 2007-10-30 - 19:39

From Pressure Test to Cool-down _ Sector 6-7 _ 30/10/2007

JPEG 6-7_october30.jpg:
6-7_october30.jpg

Comments:

Edit, attach file or add comment


Created by Main.MirkoPojer on 2007-10-30 - 19:38

From Pressure Test to Cool-down _ Sector 5-6 _ 30/10/2007

JPEG 5-6_october30.jpg:
5-6_october30.jpg

Comments:

Edit, attach file or add comment


Created by Main.MirkoPojer on 2007-10-17 - 23:15

From pressure test to cool-down - Sector 5-6 - 16/10/07

JPEG Sector_5-6_status_161007.jpg:
Sector_5-6_status_161007.jpg

Comments:

Edit, attach file or add comment


Created by Main.MirkoPojer on 2007-10-09 - 21:28

From Pressure test to Cool-down - Sector 5-6 _ 09/10/2007

JPEG 5-6.jpg:
5-6.jpg

Feedback of the meeting:

  • Problems with the soldering of the flexible of DFBAJ - To be resolded (after meeting: soldered, waiting for radiography)
  • ElQA on DFBXF.3R5 not yet done (after meeting: possibly done on Thursday)
  • Cool-down could be delayed 1 week (start on w.46)

After meeting:

  • Partial coherence test successfully performed
  • Leak in 15L6 will be repaired on Wednesday; 3 bars will be put during night to check
  • Rail for re-routing of 120 A cables on DFBLE.RR57 is in place; connection on Wednesday

Edit, attach file or add comment


Created by Main.MariaPazCasasLino on 2007-10-03 - 15:32

Warm Magnets Commissioning in point 6. Action list for the 24h run and polarity test

-Thursday 4th morning: Setup ongoing (Bernard Dubois) and pre-test from the CCC before 10:30h

-Thursday 4th,10:30h: Consignation of the converters in order to remove the covers from the magnets (Jacky Mazet)

-Thursday 4th,≈14:00h: Once the covers are removed, the converters will be deconsignée (Jacky Mazet)

-Thursday 4th,after deconsignation of the converters: Start of the 24h heat run from the CCC

-Thursday 4th,≈ 17:00h: General verification on the cables (Baptiste Lebeau)

-Friday 5th, before finishing the 24h heat run: Polarity test (Jacky Mazet)

-Friday 5th, ≈ 13:30h: Magnets and cables temperatures measurements (Jacky Mazet, Baptiste Lebeau)

-Friday 5th, ≈ 14:00h: Stop of the heat run from the CCC

-Friday 5th, just after stopping the heat run, temperatures measurements on the converters (Bernard Dubois)

-Friday 5th , consignation of the converters (Jacky Mazet)

-Friday 5th, after consignations of the converters: the covers will be put in place (Jacky Mazet)

Comments:

Edit, attach file or add comment


Created by Main.MariaPazCasasLino on 2007-10-03 - 15:15

Warm Magnets Commissioning Poin 6. Action list for the 24h heat run and polarity test

Comments:

Edit, attach file or add comment

Edit | Attach | Watch | Print version | History: r2 < r1 | Backlinks | Raw View | WYSIWYG | More topic actions
Topic revision: r2 - 2007-11-01 - JacekSzkutnik
 
    • Cern Search Icon Cern Search
    • TWiki Search Icon TWiki Search
    • Google Search Icon Google Search

    HCC All webs login