5-6.jpg:
Feedback of the meeting:
- Problems with the soldering of the flexible of DFBAJ - To be resolded (after meeting: soldered, waiting for radiography)
- ElQA on DFBXF.3R5 not yet done (after meeting: possibly done on Thursday)
- Cool-down could be delayed 1 week (start on w.46)
After meeting:
- Partial coherence test successfully performed
- Leak in 15L6 will be repaired on Wednesday; 3 bars will be put during night to check
- Rail for re-routing of 120 A cables on DFBLE.RR57 is in place; connection on Wednesday