Created by Main.AntonioVergara on 2006-10-30 - 17:06

RAT_061030.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint8x2006x10x30x17x05/RAT_061030.pdf
Comments:
Edit, attach file or add comment
Created by Main.AntonioVergara on 2006-10-27 - 15:06

RAT_061027.pdf:
https://twiki.cern.ch/twiki/pub/HCC/BlogEntryPoint8x2006x10x27x14x28/RAT_061027.pdf
Comments:
Edit, attach file or add comment
Created by Main.BlancaPereaSolano on 2006-10-23 - 18:45
The final Access system is being installed in P8. We could see the personnel and material SAS in the UA (Angels and Demons' eye recognition !!). The bake-out of the kickers in LSS8R is taking place, and should be at nominal temperature by wednesday ! The TDI is still not in place, though. We show here also the new vacuum valves.

Kickers-Bake-Out2-P8.JPG:
Kickers being baked-out

SAS-Eye.JPG:
SAS in UA87

VacuumValves-P8.JPG:
Vacuum Valve
Comments:
Edit, attach file or add comment
Created by Main.UnknownUser on 2006-10-16 - 10:58
Friday 13th October I visited the Long Straight Section in P8 up to the TI8 injection line. Here I post some photos of the status of the installation and particularly about the bake-out preparation of the MKIs. You can see how TI8 enters at the MSI level (beautiful !!). Details about collimators, and BLM are also shown. The TDI was not down yet !

IMG_2010.JPG:
Bake-out preparation for the Kickers in the LHC ring

IMG_2008.JPG:
TI8 entering the ring at the level of MSIs

IMG_2009.JPG:
BLM

IMG_2006.JPG:
TI8 warm magnets running behind the QRL

IMG_2007.JPG:
TI8 MCIs and MQIs
Comments:
Edit, attach file or add comment