CERN ROC
Plan and milestones for the creation the new ROC Canadaf
In all of the following, we will assume that both parties have read the document on the
creation of a new ROC.
Plan
Design of the Infrastructure
The needed infrastructure is defined in the general document. The infrastructure would need to be defined well in advance, at least one month/3 weeks prior to the starting of the operations.
Starting the ROC infrastructure
The following is the minimal set of tasks/functions that need to start
before the new ROC is created.
- Participation in the ROC CERN ROD activities to get familiarity with the infrastructure and procedure
- Participation to the OPS meeting
- Participation to the SA1 coordination meeting
In addition it would be good if the following started at the same time:
- Operating Nagios
- Operating the top level BDII
Tasks
For ROC Canada
- Mailing list and names
- Installation of the ROC Nagios
- Installation of the ROC bdii
- Definition of the user support infrastructure (GGUS or not GGUS)
- Installation of the certification infrastructure
- Communication of the ROC security contact and mailing list to Romain Wartel.
- Communication to GGUS of the ROC user support mailing list address
- Setting up of the VOMS dteam infrastructure
- items already done:
- Date of the creation of the new ROC: 23rd November.
- Opening of the ticket for the request of the new ROC creation to GOCDB: Done
For ROC CERN
- Notify SAM of the creation of the new ROC
- Notify SAMAP of the creation of the new ROC
- Notify the CIC portal the creation of the new ROC
- assisting in the installation of the ROC infrastructure
- Supervision of the ROD shifts
- Communicate to dteam the creation of the new ROC
- Notify Sa1 management to include the new ROC representatives in the ROC managers mailing list
- items already done:
- opening of the savannah item for the request of the new ROC creation to GGUS: Done
- E-mailing the ROC CERN sites of the change of ROC: Done
Milestones
- Date of the creation of the new ROC: 23rd November.
For ROC Canada
- Definition of the ROC infrastructure
- Participation in the ROC CERN ROD activities
- Participation to the OPS meeting
- Participation to the SA1 coordination meeting
- Identification of sites to be moved
For ROC CERN
- Checkpoint to see that the ROC infrastructure is completely defined: November 11th.
- VOMS groups created
- mailing lists communicated to SA1 management
- GOCDB entry completely defined
- Checkpoint that all relevant parties have been notified: November 5th.
After the creation of the ROC
Checks after the creation
For ROC Canada
For ROC CERN
- Check regular participation to the OPS meeting
- Monitoring of the new ROC ROD activities, assist wherever possible
- Check status of new ROC web site/twiki, assist wherever possible
- check at the end of the first and second month after the ROC is set up that they are correctly publishing
- accounting
- site availability/reliability
- Follow closely and assist in the certification of the first new site in the new ROC
--
DianaBosio - 28-Oct-2009