[LCGGridDeployment][LCG Grid Deployment]] -
CERN ROC -
ROC Incubator
Plan and milestones for the creation the new ROC Canada
- ROCName: ROC Canada
- StartDate: 28-Oct-09
- DueDate: 29-Dec-09
- Status: In Progress
In all of the following, we will assume that both parties have read the document on the
creation of a new ROC.
Plan
Design of the Infrastructure
The needed infrastructure is defined in the general document. The infrastructure would need to be defined well in advance, at least one month/3 weeks prior to the starting of the operations.
Starting the ROC infrastructure
The following is the minimal set of tasks/functions that need to start
before the new ROC is created.
- Participation in the ROC CERN ROD activities to get familiarity with the infrastructure and procedure
- Participation to the OPS meeting
- Participation to the SA1 coordination meeting
In addition it would be good if the following started at the same time:
- Operating Nagios
- Operating the top level BDII
Tasks
For ROC Canada
- Mailing list and names
- Installation of the ROC Nagios
- Installation of the ROC bdii
- Definition of the user support infrastructure (GGUS or not GGUS)
- Installation of the certification infrastructure
- Communication of the ROC security contact and mailing list to Romain Wartel.
- Communication to GGUS of the ROC user support mailing list address
- Setting up of the VOMS dteam infrastructure
- items already done:
- Date of the creation of the new ROC: 23rd November.
- Opening of the ticket for the request of the new ROC creation to GOCDB: Done
For ROC CERN
- Notify SAM of the creation of the new ROC: Done
- Notify SAMAP of the creation of the new ROC: Done
- Notify the CIC portal the creation of the new ROC: Done
- assisting in the installation of the ROC infrastructure
- Supervision of the ROD shifts: Done
- Communicate to dteam the creation of the new ROC
- Notify Sa1 management to include the new ROC representatives in the ROC managers mailing list
- items already done:
- opening of the savannah item for the request of the new ROC creation to GGUS: Done
- E-mailing the ROC CERN sites of the change of ROC: Done
Milestones
- Date of the creation of the new ROC: 23rd November.
For ROC Canada
- Definition of the ROC infrastructure
- Participation in the ROC CERN ROD activities
- Participation to the OPS meeting
- Participation to the SA1 coordination meeting
- Identification of sites to be moved
For ROC CERN
- Checkpoint to see that the ROC infrastructure is completely defined: November 11th.
- VOMS groups created
- mailing lists communicated to SA1 management
- GOCDB entry completely defined
- Checkpoint that all relevant parties have been notified: November 5th.
After the creation of the ROC
Checks after the creation
For ROC Canada
For ROC CERN
- Check regular participation to the OPS meeting
- Monitoring of the new ROC ROD activities, assist wherever possible
- Check status of new ROC web site/twiki, assist wherever possible
- check at the end of the first and second month after the ROC is set up that they are correctly publishing
- accounting
- site availability/reliability
- Follow closely and assist in the certification of the first new site in the new ROC
--
DianaBosio - 28-Oct-2009