Creation date | Description | Responsible | Status | Comments |
---|---|---|---|---|
2015-06-04 | Status of fix for Globus library (globus-gssapi-gsi-11.16-1 ) released in EPEL testing |
Andrea Manzi | ONGOING | GGUS:114076![]() |
Creation date | Description | Affected VO | Affected TF | Comments | Deadline | Completion |
---|---|---|---|---|---|---|
2015-07-02 | Provide a description of each experiment computing support structure, so tickets wrongly assigned to the T0 (via SNOW or GGUS) can be properly redirected; evaluate the creation of SNOW Functional Elements for the experiments, if this is not already the case | all | n/a | ALICE done. ATLAS draft under discussion. CMS will discuss with Maite next week. LHCb pending | July 30th. Extended to August 20th | ~50% |
Creation date | Description | Affected VO | Affected TF | Comments | Deadline | Completion |
---|---|---|---|---|---|---|
2015-06-18 | Some sites have still not enabled multicore accounting | All | Multicore Deployment | Instructions here | a.s.a.p. | Almost DONE. HERE is the list of the remaining still pending sites. |
2015-06-18 | CMS asks all T1 and T2 sites to provide Space Monitoring information to complete the picture on space usage at the sites. Please have a look at the general description and also some instructions for site admins. | CMS | - | None yet | ~10 T2 sites missing, Ticket open |